You will be cast in light of career acceptance and put individual ability to display. When you apply for a job you could have more opportunities than others. What is more, there is no interminable cover charge for our P3 Testking practice materials priced with reasonable prices for your information. We provide 24/7 customer service for all of you, please feel free to send us any questions about CIMA exam test through email or online chat, and we will always try our best to keeping our customer satisfied. P3 Testking study material will give you a better way to prepare for the actual test with its validity and reliability P3 Testking questions & answers. As we all know, the world does not have two identical leaves.
CIMA Strategic Level Case Study Exam P3 Don't hesitate.
CIMA Strategic Level Case Study Exam P3 Testking - Risk Management It is your right time to make your mark. You will have thorough training and exercises from our huge question dumps, and master every question from the detailed answer analysis. The exam software with such guarantees will clear your worries about Reliable P3 Test Dumps File exam.
During the prolonged review, many exam candidates feel wondering attention is hard to focus. But our P3 Testking real exam is high efficient which can pass the P3 Testking exam during a week. To prevent you from promiscuous state, we arranged our P3 Testking learning materials with clear parts of knowledge.
CIMA P3 Testking - SWREG payment costs more tax.
Only 20-30 hours on our P3 Testking learning guide are needed for the client to prepare for the test and it saves our client’s time and energy. Most people may wish to use the shortest time to prepare for the test and then pass the test with our P3 Testking study materials successfully because they have to spend their most time and energy on their jobs, learning, family lives and other important things. Our P3 Testking study materials can satisfy their wishes and they only spare little time to prepare for exam.
Our goal is ensure you get high passing score in the P3 Testking practice exam with less effort and less time. The accuracy of our questions and answers will the guarantee of passing actual test.
P3 PDF DEMO:
QUESTION NO: 1
An oil company has entered into a joint venture with a competing oil company to develop a new oil field. The joint venture arrangement is intended to mitigate the risks associated with developing the oil field.
The following disclosure appears in the oil company's risk report:
"Many of our large projects and operations are conducted through joint ventures. These arrangements involve complex risk allocation and indemnification arrangements and we have less control over these activities than we would have if we had full ownership and control.
Our partners may have economic or business interests that are opposed to ours, and may exercise the right to block key decisions or actions. We believe the joint arrangement is in our best interest." Which of the following statements are correct?
A. Now the shareholders know the directors are aware of the risk.
B. The risk report says nothing useful about the risk.
C. If the risk report had not reported the risk the shareholders might not have been aware of the risk.
D. The shareholders now have more useful information.
E. The risk report means that the shareholders know exactly how bad the risk is.
Answer: A,C,D
QUESTION NO: 2
In relation to the use of the adjusted present value (APV) technique, which of the following statements are correct?
A. The weighted average cost of capital - net present value technique and the APV technique will, if applied correctly, give the same answer.
B. To apply APV, the proportions of debt and equity in the capital structure must be known.
C. The interest tax shield on the project's debt must be known, or at least estimated.
D. To apply APV the actual amounts of debt and equity in the capital structure must be known.
Answer: A,C
QUESTION NO: 3
A UK based company is considering an investment of GB£1,000,000 in a project in the USA.
It is anticipated that the following cash flows will arise from this project.
The cash flows will be either US$400,000 with a probability of 40% or US$700,000 with a probability of 60% for each of the next three years; remitted to the UK at the end of each year.
Currently GB£1.00 is worth US$1.30.
The expected inflation rates in the two countries over the next four years are 2% in the UK and 4% in the US.
Applying the Purchasing Power Parity Theory, which of the following represents the expected net present value of the project in GP£ (to the nearest whole pound)?
A. GB£391,640
B. GB£554,047
C. GB£287,639
D. GB£(111,973)
Answer: C
QUESTION NO: 4
The interest rate on EUR deposits is 7%. The interest rate on GBP deposits is 5%. The spot rate is EUR/GBP0.8500. What is the one year forward rate predicted to be assuming interest rate parity holds true?
A. 0.8662
B. 0.9633
C. 0.8341
D. 0.7500
Answer: C
QUESTION NO: 5
Will owns $400,000 of shares in Company X.
Company X has a daily volatility of 1% of its share price.
Calculate the 28 day value at risk that shows the most Will can expect to lose during a 28 day period.
(Will wishes to be 90% certain that the actual loss in any month will be less than your predicted figure).
Give your answer to the nearest $000.
Answer:
$27
We can make sure that our Amazon AWS-Certified-Developer-Associate study materials have the ability to help you solve your problem, and you will not be troubled by these questions above. Huawei H13-325_V1.0 free demo is available for everyone. Scaled Agile SAFe-Agilist - You must pay more attention to the study materials. Amazon AWS-Developer-KR - We provide services 24/7 with patient and enthusiastic staff. That helping you pass the Splunk SPLK-5001 exam successfully has been given priority to our agenda.