Hope you can give our P3 Cheap Dumps exam questions full trust, we will not disappoint you. And with our P3 Cheap Dumps study materials, you are bound to pass the exam. when you buy our P3 Cheap Dumps simulating exam, our website will use professional technology to encrypt the privacy of every user to prevent hackers from stealing. Through our short-term special training You can quickly grasp IT professional knowledge, and then have a good preparation for your exam. We promise that we will do our best to help you pass the CIMA certification P3 Cheap Dumps exam. The goal of our P3 Cheap Dumps exam questions is always to get you through the P3 Cheap Dumps exam.
CIMA Strategic Level Case Study Exam P3 As the saying goes, practice makes perfect.
CIMA Strategic Level Case Study Exam P3 Cheap Dumps - Risk Management As the most professional supplier on the site of IT certification test currently , we provide a comprehensive after-sales service. Actions speak louder than words. You are supposed to learn to make a rational plan of life.
If you want to through CIMA P3 Cheap Dumps certification exam, add the Goldmile-Infobiz CIMA P3 Cheap Dumps exam training to Shopping Cart quickly! The community has a lot of talent, people constantly improve their own knowledge to reach a higher level. But the country's demand for high-end IT staff is still expanding, internationally as well.
CIMA P3 Cheap Dumps - Of course, their income must be very high.
Are you still searching proper P3 Cheap Dumps exam study materials, or are you annoying of collecting these study materials? As the professional IT exam dumps provider, Goldmile-Infobiz has offered the complete P3 Cheap Dumps exam materials for you. So you can save your time to have a full preparation of P3 Cheap Dumps exam.
The Goldmile-Infobiz's CIMA P3 Cheap Dumps exam training materials is so successful training materials. It is most suitable for you, quickly select it please.
P3 PDF DEMO:
QUESTION NO: 1
Will owns $400,000 of shares in Company X.
Company X has a daily volatility of 1% of its share price.
Calculate the 28 day value at risk that shows the most Will can expect to lose during a 28 day period.
(Will wishes to be 90% certain that the actual loss in any month will be less than your predicted figure).
Give your answer to the nearest $000.
Answer:
$27
QUESTION NO: 2
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C
QUESTION NO: 3
A UK based company is considering an investment of GB£1,000,000 in a project in the USA.
It is anticipated that the following cash flows will arise from this project.
The cash flows will be either US$400,000 with a probability of 40% or US$700,000 with a probability of 60% for each of the next three years; remitted to the UK at the end of each year.
Currently GB£1.00 is worth US$1.30.
The expected inflation rates in the two countries over the next four years are 2% in the UK and 4% in the US.
Applying the Purchasing Power Parity Theory, which of the following represents the expected net present value of the project in GP£ (to the nearest whole pound)?
A. GB£391,640
B. GB£554,047
C. GB£287,639
D. GB£(111,973)
Answer: C
QUESTION NO: 4
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C
QUESTION NO: 5
In relation to the use of the adjusted present value (APV) technique, which of the following statements are correct?
A. The weighted average cost of capital - net present value technique and the APV technique will, if applied correctly, give the same answer.
B. To apply APV, the proportions of debt and equity in the capital structure must be known.
C. The interest tax shield on the project's debt must be known, or at least estimated.
D. To apply APV the actual amounts of debt and equity in the capital structure must be known.
Answer: A,C
Your success is the success of our Goldmile-Infobiz, and therefore, we will try our best to help you obtain Amazon SAP-C02 exam certification. Amazon AWS-Developer - Goldmile-Infobiz can provide professional and high quality products. There are quite a few candidates of VMware 250-614 certification exam have already started his career, and there are many examinees facing other challenges in life, so we provide candidates with the most efficient review method of VMware 250-614 exam. ACAMS CAMS-KR - You can also request we provide you with the latest dumps at any time. If you prepare based on our PMI PMP-KR exam simulations files, you will feel easy to clear exam once certainly.