After you have studied for twenty to thirty hours on our P3 Instant Access exam questions, you can take the test. And your pass rate will reach 99%. With our users all over the world, you really should believe in the choices of so many people. Being considered the most authentic brand in this career, our professional experts are making unremitting efforts to provide our customers the latest and valid {CertName} exam simulation. With the development of society, the P3 Instant Access certificate in our career field becomes a necessity for developing the abilities. After 20 to 30 hours of studying P3 Instant Access exam materials, you can take the exam and pass it for sure.
The P3 Instant Access training materials are so very helpful.
The experts from our company designed the three different versions of P3 - Risk Management Instant Access test torrent with different functions. You can choose the most suitable version to learn. Of course, if you want to, you can choose more than one version to prepare your P3 Valid Mock Test exam.
There are so many specialists who join together and contribute to the success of our P3 Instant Access guide quiz just for your needs. As well as responsible and patient staff who has being trained strictly before get down to business and interact with customers on our P3 Instant Access exam questions. You can contact with our service, and they will give you the most professional guide.
CIMA P3 Instant Access - So with it you can easily pass the exam.
You can imagine that you just need to pay a little money for our P3 Instant Access exam prep, what you acquire is priceless. So it equals that you have made a worthwhile investment. Firstly, you will learn many useful knowledge and skills from our P3 Instant Access exam guide, which is a valuable asset in your life. After all, no one can steal your knowledge. In addition, you can get the valuable P3 Instant Access certificate.
All the IT professionals are familiar with the CIMA P3 Instant Access exam. And all of you dream of owning the most demanding certification.
P3 PDF DEMO:
QUESTION NO: 1
A UK based company is considering an investment of GB£1,000,000 in a project in the USA.
It is anticipated that the following cash flows will arise from this project.
The cash flows will be either US$400,000 with a probability of 40% or US$700,000 with a probability of 60% for each of the next three years; remitted to the UK at the end of each year.
Currently GB£1.00 is worth US$1.30.
The expected inflation rates in the two countries over the next four years are 2% in the UK and 4% in the US.
Applying the Purchasing Power Parity Theory, which of the following represents the expected net present value of the project in GP£ (to the nearest whole pound)?
A. GB£391,640
B. GB£554,047
C. GB£287,639
D. GB£(111,973)
Answer: C
QUESTION NO: 2
Will owns $400,000 of shares in Company X.
Company X has a daily volatility of 1% of its share price.
Calculate the 28 day value at risk that shows the most Will can expect to lose during a 28 day period.
(Will wishes to be 90% certain that the actual loss in any month will be less than your predicted figure).
Give your answer to the nearest $000.
Answer:
$27
QUESTION NO: 3
In relation to the use of the adjusted present value (APV) technique, which of the following statements are correct?
A. The weighted average cost of capital - net present value technique and the APV technique will, if applied correctly, give the same answer.
B. To apply APV, the proportions of debt and equity in the capital structure must be known.
C. The interest tax shield on the project's debt must be known, or at least estimated.
D. To apply APV the actual amounts of debt and equity in the capital structure must be known.
Answer: A,C
QUESTION NO: 4
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C
QUESTION NO: 5
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C
Snowflake GES-C01 - We believe that the trial version provided by our company will help you know about our study materials well and make the good choice for yourself. Fortinet NSE4_FGT_AD-7.6 - So that you can get the latest exam information in time. HP HPE3-CL04 - Now you also have the opportunity to contact with the Risk Management test guide from our company. Goldmile-Infobiz CIMA Pegasystems PEGACPCSD25V1 dumps are an indispensable material in the certification exam. After you use our products, our ACAMS CAMS-CN study materials will provide you with a real test environment before the ACAMS CAMS-CN exam.