P3 Latest Exam Format - P3 Reliable Exam Camp Questions & Risk Management - Goldmile-Infobiz

Goldmile-Infobiz's providing training material is very close to the content of the formal examination. Through our short-term special training You can quickly grasp IT professional knowledge, and then have a good preparation for your exam. We promise that we will do our best to help you pass the CIMA certification P3 Latest Exam Format exam. This is what we should do for you as a responsible company. But our P3 Latest Exam Format study materials have the high pass rate as 98% to 100%, so it is guarantee for you to pass. We will provide one year free update service for those customers who choose Goldmile-Infobiz's products.

CIMA Strategic Level Case Study Exam P3 But it is not easy to pass the exam.

If you are still hesitate to choose our Goldmile-Infobiz, you can try to free download part of CIMA P3 - Risk Management Latest Exam Format exam certification exam questions and answers provided in our Goldmile-Infobiz. One is PDF, and other is software, it is easy to download. The IT professionals and industrious experts in Goldmile-Infobiz make full use of their knowledge and experience to provide the best products for the candidates.

Goldmile-Infobiz can not only achieve your dreams, but also provide you one year of free updates and after-sales service. The answers of Goldmile-Infobiz's exercises is 100% correct and they can help you pass CIMA certification P3 Latest Exam Format exam successfully. You can free download part of practice questions and answers of CIMA certification P3 Latest Exam Format exam online as a try.

CIMA P3 Latest Exam Format - To selecte Goldmile-Infobiz is to choose success.

There are quite a few candidates of P3 Latest Exam Format certification exam have already started his career, and there are many examinees facing other challenges in life, so we provide candidates with the most efficient review method of P3 Latest Exam Format exam. In order to let you be rest assured to purchase our products, we offer a variety of versions of the samples of P3 Latest Exam Format study materials for your trial. We've helped countless examinees pass P3 Latest Exam Format exam, so we hope you can realize the benefits of our software that bring to you.

You can also request we provide you with the latest dumps at any time. If you want to know the latest exam questions, even if you have passed the certification test, Goldmile-Infobiz will also free update exam dumps for you.

P3 PDF DEMO:

QUESTION NO: 1
M plc has a $2 million loan outstanding on which the interest rate is reset every 6 months for the following 6 months and the interest is payable at the end of that 6-month period. The next
6-monthly reset period starts in
3 months and the treasurer of M plc thinks that interest rates are likely to rise between now and then.
Current 6-month rates are 7.2% and the treasurer can get a rate of 7.7% for a 6-month forward rate agreement (FRA) starting in 3 months' time. By transacting an FRA the treasurer can lock in a rate today of 7.7%.
If interest rates are 8.5% in 3 months' time, what will the net amount payable be?
Give your answer to the nearest thousand dollars.
Answer:
$77000

QUESTION NO: 2
P Ltd manufactures and sells electrical goods through retail outlets.
N is P Ltd's Sales Director. He has been recently promoted from a senior sales position with
P Ltd. He has been forced to spend the first six months as Sales Director on dealing with an administrative mess left behind by the previous sales director.
You are a Senior Management Accountant at P Ltd. You have worked with N for many years.
N has worked hard and has made many changes that have brought significant benefit to the business.
N has asked you to postpone the recording of some purchase invoices so that he will meet his quarterly targets on profit margin.
What should you do?
A. Collect all the facts, distance yourself from the situation but say nothing.
B. Write up the facts of the issue and put it on your files.
C. Do nothing, no rules have been broken, tell N that you cannot do as he asks and that he needs to abide by the professional codes.
D. Document the situation and present the facts to your manager.
Answer: C

QUESTION NO: 3
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C

QUESTION NO: 4
RFG is considering a major expansion that will result in a more diversified business model.
At present, RFG's market capitalisation is $240 million. This is based on a beta of 1.6. The risk free rate is 4% and the market rate of return is 9%. RFG is financed entirely by equity.
The company generates an annual cash surplus of $28.8 million.
The expansion will cost $50 million and will generate future cash flows of $12 million in perpetuity. This new business will reduce RFG's beta to 1.4.
Calculate the adjusted present value of the expansion.
A. $59 million
B. $321 million
C. $131 million
D. $81 million
Answer: D

QUESTION NO: 5
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C

If you prepare based on our PRINCE2 PRINCE2-Foundation exam simulations files, you will feel easy to clear exam once certainly. Microsoft SC-200 - All Of IT staff knows it is very difficult to get IT certificate. Purchasing valid Amazon AIF-C01-KR exam dumps is not a cheap thing for some candidates in the internet since there is so much different advertisement. No matter which process you are preparing for SAP C-SIGPM-2403 exam, our exam software will be your best helper. Google Associate-Cloud-Engineer - Chance favors the prepared mind.