P3 Latest Exam Sample Questions - Latest Exam P3 Dumps Materials & Risk Management - Goldmile-Infobiz

Once you receive our email, just begin to your new learning journey. Normally, you just need to wait for about five to ten minutes after you purchase our P3 Latest Exam Sample Questions learning braindumps. If you do not receive our P3 Latest Exam Sample Questions study materials, please contact our online workers. It is universally accepted that the competition in the labor market has become more and more competitive in the past years. In order to gain some competitive advantages, a growing number of people have tried their best to pass the P3 Latest Exam Sample Questions exam. All popular official tests have been included in our P3 Latest Exam Sample Questions study materials.

CIMA Strategic Level Case Study Exam P3 Your work efficiency will far exceed others.

CIMA Strategic Level Case Study Exam P3 Latest Exam Sample Questions - Risk Management So, users can flexibly adjust their learning plans according to their learning schedule. Our P3 Valid Exam Collection Free exam torrent is absolutely safe and virus-free. When it comes to buying something online (for example, P3 Valid Exam Collection Free exam torrent), people who are concerned with privacy protection are often concerned about their personal information during the purchase process.

Under the leadership of a professional team, we have created the most efficient learning P3 Latest Exam Sample Questions training guide for our users. Our users use their achievements to prove that we can get the most practical knowledge in the shortest time. P3 Latest Exam Sample Questions exam questions are tested by many users and you can rest assured.

CIMA P3 Latest Exam Sample Questions - It can maximize the efficiency of your work.

As is known to us, there are best sale and after-sale service of the P3 Latest Exam Sample Questions study materials all over the world in our company. Our company has employed a lot of excellent experts and professors in the field in the past years, in order to design the best and most suitable P3 Latest Exam Sample Questions study materials for all customers. More importantly, it is evident to all that the P3 Latest Exam Sample Questions study materials from our company have a high quality, and we can make sure that the quality of our products will be higher than other study materials in the market. If you want to pass the P3 Latest Exam Sample Questions exam and get the related certification in the shortest time, choosing the P3 Latest Exam Sample Questions study materials from our company will be in the best interests of all people. We can make sure that it will be very easy for you to pass your exam and get the related certification in the shortest time that beyond your imagination.

You only need to download the Goldmile-Infobiz CIMA P3 Latest Exam Sample Questions exam training materials, namely questions and answers, the exam will become very easy. Goldmile-Infobiz guarantee that you will be able to pass the exam.

P3 PDF DEMO:

QUESTION NO: 1
P Ltd manufactures and sells electrical goods through retail outlets.
N is P Ltd's Sales Director. He has been recently promoted from a senior sales position with
P Ltd. He has been forced to spend the first six months as Sales Director on dealing with an administrative mess left behind by the previous sales director.
You are a Senior Management Accountant at P Ltd. You have worked with N for many years.
N has worked hard and has made many changes that have brought significant benefit to the business.
N has asked you to postpone the recording of some purchase invoices so that he will meet his quarterly targets on profit margin.
What should you do?
A. Collect all the facts, distance yourself from the situation but say nothing.
B. Write up the facts of the issue and put it on your files.
C. Do nothing, no rules have been broken, tell N that you cannot do as he asks and that he needs to abide by the professional codes.
D. Document the situation and present the facts to your manager.
Answer: C

QUESTION NO: 2
M plc has a $2 million loan outstanding on which the interest rate is reset every 6 months for the following 6 months and the interest is payable at the end of that 6-month period. The next
6-monthly reset period starts in
3 months and the treasurer of M plc thinks that interest rates are likely to rise between now and then.
Current 6-month rates are 7.2% and the treasurer can get a rate of 7.7% for a 6-month forward rate agreement (FRA) starting in 3 months' time. By transacting an FRA the treasurer can lock in a rate today of 7.7%.
If interest rates are 8.5% in 3 months' time, what will the net amount payable be?
Give your answer to the nearest thousand dollars.
Answer:
$77000

QUESTION NO: 3
Which of the following represents the greatest risk associated with introducing a system of post-completion audit for investment projects?
A. The audit itself will waste time.
B. The entity may withdraw from a project without good cause.
C. Decision makers may be deterred from taking responsible risks.
D. The entity will realise that its approach to project appraisal is flawed.
Answer: C

QUESTION NO: 4
H is a senior production manager for P Ltd which is about to make a strategic decision on setting up a new production line requiring $3 million of new specialist equipment.
H's daughter is friends with and goes to school with the daughter of T, the sales manager in
KK Ltd. KK Ltd is a potential supplier of the specialist equipment that P Ltd requires.
T owns a holiday home. H's daughter regularly accompanies T's daughter on family vacations at this holiday home, all at T's expense.
H is the only person working for P Ltd who is qualified to select the specialist equipment. KK
Ltd will definitely bid for the sale.
What should H do?
A. H should declare an interest and withdraw from the assessment process.
B. H should permit KK Ltd to bid, but should insist that T should not be involved.
C. H should declare an interest, giving details of his daughter's friendship with T's daughter, but should participate fully in the assessment process.
D. H should exclude KK Ltd from the bidding process.
Answer: C

QUESTION NO: 5
RFG is considering a major expansion that will result in a more diversified business model.
At present, RFG's market capitalisation is $240 million. This is based on a beta of 1.6. The risk free rate is 4% and the market rate of return is 9%. RFG is financed entirely by equity.
The company generates an annual cash surplus of $28.8 million.
The expansion will cost $50 million and will generate future cash flows of $12 million in perpetuity. This new business will reduce RFG's beta to 1.4.
Calculate the adjusted present value of the expansion.
A. $59 million
B. $321 million
C. $131 million
D. $81 million
Answer: D

You can apply for many types of Fortinet NSE6_SDW_AD-7.6 exam simulation at the same time. Databricks Associate-Developer-Apache-Spark-3.5 - It is the leader in all training materials. Fortinet FCP_FSA_AD-5.0 - You can find their real comments in the comments sections. HP HPE7-A01 - Dreams and hopes are important, but more important is to go to practice and prove. F5 401 - Many people always are stopped by the difficult questions.