BA2 Explanations - Cima Fundamentals Of Management Accounting Reliable Test Questions Vce - Goldmile-Infobiz

Fourthly, Goldmile-Infobiz exam dumps have two versions: PDF and SOFT version. With the two versions, the candidates can pass their exam with ease. What do you think of using Goldmile-Infobiz CIMA BA2 Explanations exam dumps? Goldmile-Infobiz CIMA BA2 Explanations certification training dumps, it may be said, is the most excellent reference materials among all exam-related reference materials. A bad situation can show special integrity. When to face of a difficult time, only the bravest people could take it easy. Different person has different goals, but our Goldmile-Infobiz aims to help you successfully pass BA2 Explanations exam.

CIMA Business Accounting BA2 Goldmile-Infobiz is worthy your trust.

To help you get the CIMA exam certification, we provide you with the best valid BA2 - Fundamentals of management accounting Explanations pdf prep material. BA2 Valid Practice Questions Ppt exam seems just a small exam, but to get the BA2 Valid Practice Questions Ppt certification exam is to be reckoned in your career. Such an international certification is recognition of your IT skills.

To ensure your 100% satisfaction, BA2 Explanations free demo are available for the certification exam you're going to take before you purchased. All our BA2 Explanations dumps collection is quite effectively by millions of people that passed BA2 Explanations real exam and become professionals in IT filed. You will never regret choosing our BA2 Explanations test answers as your practice materials because we will show you the most authoritative study guide.

CIMA BA2 Explanations - Our key advantages are that 1.

We have a lasting and sustainable cooperation with customers who are willing to purchase our BA2 Explanations actual exam. We try our best to renovate and update our BA2 Explanations study materials in order to help you fill the knowledge gap during your learning process, thus increasing your confidence and success rate. At the same time, BA2 Explanations preparation baindumps can keep pace with the digitized world by providing timely application. You will never fell disappointed with our BA2 Explanations exam quiz.

If you are urgent to pass exam our exam materials will be suitable for you. Mostly you just need to remember the questions and answers of our CIMA BA2 Explanations exam review questions and you will clear exams.

BA2 PDF DEMO:

QUESTION NO: 1
A company is appraising two projects. Both projects are for five years. Details of the two projects are as follows.
Based on the above information, which of the following statements is correct?
A. The annuity factor for project A would double the annuity factor for project B.
B. An annuity could be used to calculate the net present value of the projects.
C. The annuity factor for project A would be lower than the annuity factor for the project
D. A perpetuity could be used to calculate the net present value of the projects.
Answer: B

QUESTION NO: 2
The gradient of the line plotted on a profit/volume (PV) graph is determined by:
A. The number of units sold
B. The fixed costs
C. The margin of safety
D. The profit/volume ratio
Answer: D

QUESTION NO: 3
The year-to-date results at the end of month 9 included sales revenue of $3,600,000 and variable costs of
$2,100,000.
During month 10, sales revenue was $450,000 and variable costs were $270,000.
What year-to-date contribution to sales ratio (C/S ratio) would be reported at the end of month 10?
A. 70,9%
B. 41,5%
C. 40,0%
D. 58,5%
Answer: D

QUESTION NO: 4
CL produces a household detergent in a single process. Information for this process for last month is as follows:
(a) Materials input - 11,000 Litres at £2.00 per litre.
(b) Conversion costs - £23,000
(c) Output during the month - 8,000 litres.
(d) There were 2,000 units of closing work in progress which was complete as to materials and 35% complete as to conversion.
(e) Normal loss for the month was 5% of input and all losses have a scrap value of 50p per litre.
(f) There is no opening work in progress.
The value of finished output during the month (to the nearest £) was:
Answer:
£36741

QUESTION NO: 5
Refer to the exhibit.
The profit/volume graph below has been prepared for a product for which the following data are available for a period:
Selling price - $28 per unit
Variable cost - $23 per unit
Fixed cost - $4 per unit
Forecast sales volume is 1,000 units each period.
The value of P in units is:
Answer:
800

With the high pass rate as 98% to 100%, we can proudly claim that we are unmatched in the market for our accurate and latest Huawei H19-338 exam dumps. We offer you the most accurate Citrix 1Y0-204 exam answers that will be your key to pass the certification exam in your first try. By selecting our Huawei H19-484_V1.0 training material, you will be able to pass the Huawei H19-484_V1.0 exam in the first attempt. The Microsoft AZ-140 test answers are tested and approved by our certified experts and you can check the accuracy of our questions from our free demo. Now you can pass CIMA IBM C1000-204 exam without going through any hassle.