Do not satisfied with using shortcuts during your process, regular practice with our MB-320 Questions exam prep will be easy. Tens of thousands of people has achieved success with our MB-320 Questionsstudy questions, you can absolutely do it. And you will find that passing the MB-320 Questions exam is as easy as pie. If you choose our MB-320 Questions practice engine, you are going to get the certification easily. Just make your choice and purchase our MB-320 Questions training quiz and start your study now! If you come to visit our website more times, you will buy our MB-320 Questions practice engine at a more favorable price.
Microsoft Dynamics 365 MB-320 And we have become a popular brand in this field.
As a market leader, our company is able to attract quality staffs on our MB-320 - Microsoft Dynamics 365 Supply Chain Management, Manufacturing Questions exam materials , it actively seeks out those who are energetic, persistent, and professional to various MB-320 - Microsoft Dynamics 365 Supply Chain Management, Manufacturing Questions certificate and good communicator. For many people, it’s no panic passing the Exam MB-320 Guide exam in a short time. Luckily enough,as a professional company in the field of Exam MB-320 Guide practice questions ,our products will revolutionize the issue.
A good reputation is the driving force for our continued development. Our company has absolute credit, so you can rest assured to buy our MB-320 Questions test guides. When you buy things online, you must ensure the security of online purchasing, otherwise your rights will be harmed.
Microsoft MB-320 Questions - You can spend more time doing other things.
Maybe you want to keep our MB-320 Questions exam guide available on your phone. Don't worry, as long as you have a browser on your device, our App version of our MB-320 Questions study materials will perfectly meet your need. That is to say that we can apply our App version on all kinds of eletronic devices, such as IPAD, computer and so on. And this version of our MB-320 Questions practice engine can support a lot of systems, such as Windows, Mac,Android and so on.
Our company's experts are daily testing our MB-320 Questions study guide for timely updates. So we solemnly promise the users, our products make every effort to provide our users with the latest learning materials.
MB-320 PDF DEMO:
QUESTION NO: 1
A company implements Dynamics 365 for Finance and Operations.
Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:
* Locate a supermarket at the subcontractor building.
* Support picking and shipping activity tracking.
* Associate costs of transporting materials between the locations in the cost of the finished product.
You need to modify the production flow.
A company implements Dynamics 365 for Finance and Operations.
Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:
* Locate a supermarket at the subcontractor building.
* Support picking and shipping activity tracking.
* Associate costs of transporting materials between the locations in the cost of the finished product.
You need to modify the production flow.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A. Modify the tumble polish activity and assign it to the subcontractor.
B. Create a resource and work cell resource group for the subcontractor.
C. Create a new production flow version.
D. Modify the tumble polish operation and associate it with the subcontractor.
E. Create transfer activities and assign thereto the subcontractor.
Answer: A,B,E
Explanation
References:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/manage- subcontract-work-produ
QUESTION NO: 2
A company overstates on-hand raw materials due to the time it takes to post raw materials as consumed when production orders are processed.
All items used to manufacture finished goods must be consumed when a finished good is reported as finished.
You must not change all bill of materials lines to use the option of flushing principal.
You need to ensure that all production orders consume raw materials at Report as finished.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Explanation
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/production- parameters-manufac
QUESTION NO: 3
A company uses Process manufacturing.
You need to review formulas and how the different ingredient types impact the batch balancing process.
Which ingredient types should you use? To answer, drag the appropriate ingredient types to the correct scenarios. Each ingredient may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
Answer:
Explanation
References:
https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production- control/batch-balanci
QUESTION NO: 4
A company uses Process manufacturing for most products and Discreet manufacturing for other products. The company is creating a formula for a new product. The new item will be used to make a name brand product and two generic brand products.
This item has the following requirements:
* Production of the name brand and generic products must use the same formula.
* The company must produce all three items at the same time.
You need to create a produced item that can make two generic items and one main item.
How should you set up the item?
A. Create the name brand item as a Bills of material production type item.
Create the two generic items as a sub-assembly on the Bills of material for the name brand product.
B. Create the name brand product as the main product and use a formula production type. Create the two generic items as a formula planning production type planning items. Copy the formula from the name brand item into each of the generic items.
C. Create the name brand product as the main product and use a formula production type.
Create the two generic products as co-products as part of the formula for the name brand product.
D. Create the name brand item as a Bills of material production type item.
Add the two generic items on the Bills of material for the name brand product and use line type phantom.
Answer: C
QUESTION NO: 5
A company is looking to use Dynamics 365 for Finance and Operations.
The company is in the process of redesigning and retooling an existing manufacturing plant to group similar, cellular operations to improve efficiency and minimize wasted time between operations.
They want to locate raw materials close to where they are needed without losing reorder visibility.
You need to set up their environment.
Which kind of production type should you implement?
A. Manufacturing execution
B. Discrete manufacturing
C. Process manufacturing
D. Lean manufacturing
Answer: D
A lot of things can’t be tried before buying or the product trail will charge a certain fee, but our IIA IIA-CIA-Part3-KR exam questions are very different, you can try it free before you buy it. By visit our website, the user can obtain an experimental demonstration, free after the user experience can choose the most appropriate and most favorite Fortinet NSE5_SSE_AD-7.6 exam questions download. You can use your smart phones, laptops, the tablet computers or other equipment to download and learn our CIPS L4M2 learning dump. SAP C-S4CPR-2508 - What are you waiting for? Just buy our exam braindumps! So they hope that they can be devoting all of their time to preparing for the IIA IIA-CIA-Part2-KR exam, but it is very obvious that a lot of people have not enough time to prepare for the important exam.