With our software version of our PSM-II Fee guide braindumps, you can practice and test yourself just like you are in a real exam for our PSM-II Fee study materials have the advandage of simulating the real exam. The results of your PSM-II Fee exam will be analyzed and a statistics will be presented to you. So you can see how you have done and know which kinds of questions of the PSM-II Fee exam are to be learned more. Whatever exam you choose to take, Goldmile-Infobiz training dumps will be very helpful to you. Because all questions in the actual test are included in Goldmile-Infobiz practice test dumps which provide you with the adequate explanation that let you understand these questions well. You can see the demo, the form of the software and part of our titles.
Professional Scrum Master PSM-II Then you will be confident in the actual test.
The PSM-II - Professional Scrum Master level II (PSM II) Fee quiz torrent we provide is compiled by experts with profound experiences according to the latest development in the theory and the practice so they are of great value. Scrum New PSM-II Exam Cram Review exam cram PDF will be great helper for your coming exam definitely. The secret of success is constancy to purpose.
The new supplemental updates will be sent to your mailbox if there is and be free. Because we promise to give free update of our PSM-II Fee learning materials for one year to all our customers. Generally speaking, you can achieve your basic goal within a week with our PSM-II Fee study guide.
Scrum PSM-II Fee - We have benefited a lot from those changes.
The PSM-II Fee practice questions that are best for you will definitely make you feel more effective in less time. The cost of PSM-II Fee studying materials is really very high. Selecting our study materials is definitely your right decision. Of course, you can also make a decision after using the trial version. With our PSM-II Fee real exam, we look forward to your joining. And our PSM-II Fee exam braindumps will never let you down.
In our software version of the PSM-II Fee exam dumps, the unique point is that you can take part in the practice test before the real PSM-II Fee exam. You never know what you can get till you try.
PSM-II PDF DEMO:
QUESTION NO: 1
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.
QUESTION NO: 2
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
QUESTION NO: 3
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.
QUESTION NO: 4
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.
QUESTION NO: 5
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C
There is a lot of data to prove that our Snowflake GES-C01 practice guide has achieved great success. EMC D-PWF-DS-01 - Are you still worried about the exam? Don’t worry! And our Lpi 101-500 real study braindumps can help you get better and better reviews. So our Microsoft PL-600 study braindumps are a valuable invest which cost only tens of dollars but will bring you permanent reward. ECCouncil 212-82 - You must also realize that you really need to improve your strength.