Our PSM-II Dump Collection quiz guide’ reputation for compiling has created a sound base for our beautiful future business. We are clearly concentrated on the international high-end market, thereby committing our resources to the specific product requirements of this key market sector, as long as cater to all the users who wants to get the test Scrum certification. Knowledge is a great impetus for the progress of human civilization. Then after deliberate considerations, you can directly purchase the most suitable one for yourself. If you want to check the quality and validity of our PSM-II Dump Collection exam questions, then you can click on the free demos on the website. If you choose our products, you will become a better self.
PSM-II Dump Collection study engine is so amazing.
Professional Scrum Master PSM-II Dump Collection - Professional Scrum Master level II (PSM II) Goldmile-Infobiz's expert team is a large team composed of senior IT professionals. By devoting in this area so many years, we are omnipotent to solve the problems about the PSM-II Latest Test Simulator learning questions with stalwart confidence. we can claim that only studing our PSM-II Latest Test Simulator study guide for 20 to 30 hours, then you will pass the exam for sure.
Goldmile-Infobiz is a website for Scrum certification PSM-II Dump Collection exam to provide a short-term effective training. Scrum PSM-II Dump Collection is a certification exam which is able to change your life. IT professionals who gain Scrum PSM-II Dump Collection authentication certificate must have a higher salary than the ones who do not have the certificate and their position rising space is also very big, who will have a widely career development prospects in the IT industry in.
Scrum PSM-II Dump Collection - Continuous improvement is a good thing.
Scrum PSM-II Dump Collection certification exam is very important for every IT person. With this certification you will not be eliminated, and you will be a raise. Some people say that to pass the Scrum PSM-II Dump Collection exam certification is tantamount to success. Yes, this is true. You get what you want is one of the manifestations of success. Goldmile-Infobiz of Scrum PSM-II Dump Collection exam materials is the source of your success. With this training materials, you will speed up the pace of success, and you will be more confident.
This can be borne out by the large number of buyers on our website every day. And our pass rate of our PSM-II Dump Collection exam braindumps is high as 98% to 100%.
PSM-II PDF DEMO:
QUESTION NO: 1
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C
QUESTION NO: 2
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.
QUESTION NO: 3
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C
QUESTION NO: 4
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.
QUESTION NO: 5
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
Amazon DOP-C02-KR - So, it can save much time for us. Our IAPP CIPP-E study guide is carefully edited and reviewed by our experts. SAP C-ARCIG-2508 - This is because IT experts can master the question point well, so that all questions the candidates may come across in the actual test are included in Goldmile-Infobiz exam dumps. In addition, the passing rate of our Scaled Agile SAFe-Agilist study materials is very high, and we are very confident to ensure your success. And then are what materials your worthwhile option? Do you have chosen Goldmile-Infobiz Scrum ServiceNow CIS-SPM real questions and answers? If so, you don't need to worry about the problem that can't pass the exam.