In order to improve the value of your career, you must pass this certification exam. The exam questions and answers designed by Goldmile-Infobiz contain different targeted, and have wide coverage. There is no any other books or other information can transcend it. If you would like to sail through the test, come on and try it. To pass Scrum PSM-II Pdf Vce certification exam seems to be a very difficult task. Goldmile-Infobiz guarantee exam success rate of 100% ratio, except no one.
Professional Scrum Master PSM-II To selecte Goldmile-Infobiz is to choose success.
There are quite a few candidates of PSM-II - Professional Scrum Master level II (PSM II) Pdf Vce certification exam have already started his career, and there are many examinees facing other challenges in life, so we provide candidates with the most efficient review method of PSM-II - Professional Scrum Master level II (PSM II) Pdf Vce exam. If you buy Goldmile-Infobiz exam dumps, you will obtain free update for a year. Once the dumps update, Goldmile-Infobiz will immediately send the latest certification training materials to your mailbox.
PSM-II Pdf Vce exam simulations files can help you obtain an IT certification. As we all know IT exam cost is very high, most people have to try more than one time so that they can pass exam. If you prepare based on our PSM-II Pdf Vce exam simulations files, you will feel easy to clear exam once certainly.
Scrum PSM-II Pdf Vce - Chance favors the prepared mind.
Sometimes if you want to pass an important test, to try your best to exercise more questions is very necessary, which will be met by our PSM-II Pdf Vce exam software, and the professional answer analysis also can help you have a better understanding. the multiple versions of free demo of PSM-II Pdf Vce exam materials can be offered in our website. Try to find which version is most to your taste; we believe that our joint efforts can make you pass PSM-II Pdf Vce certification exam.
We are ready to show you the most reliable PSM-II Pdf Vce pdf vce and the current exam information for your preparation of the test. Before you try to attend the PSM-II Pdf Vce practice exam, you need to look for best learning materials to easily understand the key points of PSM-II Pdf Vce exam prep.
PSM-II PDF DEMO:
QUESTION NO: 1
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
QUESTION NO: 2
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.
QUESTION NO: 3
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.
QUESTION NO: 4
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
A. Ask the Development Team member to share the issue with the team as soon as possible.
B. Notify the test team.
C. Add a Product Backlog item to address the security issue.
D. Wait until the Sprint Retrospective to add security to the definition of "Done".
Answer: A
Explanation:
It is best to coach the Development Team members to collaborate on issues regardless of severity.
They may consult the Scrum Master of Product Owner if needed.
QUESTION NO: 5
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.
HITRUST CCSFP - Goldmile-Infobiz Scrum exam study material can simulate the actual test and give you an interactive experience during the practice. Passing ITIL ITIL-4-Foundation practice exam is not so easy and need to spend much time to prepare the training materials, that's the reason that so many people need professional advice for ITIL ITIL-4-Foundation exam prep. While, the HashiCorp Terraform-Associate-003 exam dumps provided by Goldmile-Infobiz site will be the best valid training material for you. The way to pass the Workday Workday-Pro-HCM-Reporting actual test is diverse. We are a team of IT professionals that provide our customers with the up-to-date Huawei H19-338-ENU study guide and the current certification exam information.
Updated: May 27, 2022