PSM-II Valid Study Plan exam is a very important Scrum's certification exam. But if you want to get a Scrum certification, you must pass the exam. Now there are many IT professionals in the world and the competition of IT industry is very fierce. Our PSM-II Valid Study Plan practice engine can offer you the most professional guidance, which is helpful for your gaining the certificate. And our PSM-II Valid Study Plan learning guide contains the most useful content and keypoints which will come up in the real exam. Don't need a lot of time and money, only 30 hours of special training, and you can easily pass your first time to attend Scrum certification PSM-II Valid Study Plan exam.
Because it can help you prepare for the PSM-II Valid Study Plan exam.
Professional Scrum Master PSM-II Valid Study Plan - Professional Scrum Master level II (PSM II) The material including practice questions and answers. According to the survey from our company, the experts and professors from our company have designed and compiled the best New PSM-II Braindumps Pdf cram guide in the global market. A lot of people have given up when they are preparing for the New PSM-II Braindumps Pdf exam.
Goldmile-Infobiz Scrum PSM-II Valid Study Plan exam materials contain the complete unrestricted dump. So with it you can easily pass the exam. Goldmile-Infobiz Scrum PSM-II Valid Study Plan exam training materials is a good guidance.
Scrum PSM-II Valid Study Plan - Our research materials have many advantages.
Since it was founded, our Goldmile-Infobiz has more and more perfect system, more rich questiondumps, more payment security, and better customer service. Now the PSM-II Valid Study Plan exam dumps provided by Goldmile-Infobiz have been recognized by masses of customers, but we will not stop the service after you buy. We will inform you at the first time once the PSM-II Valid Study Plan exam software updates, and if you can't fail the PSM-II Valid Study Plan exam we will full refund to you and we are responsible for your loss.
You really can't find a more cost-effective product than PSM-II Valid Study Plan learning quiz! Our company wants more people to be able to use our products.
PSM-II PDF DEMO:
QUESTION NO: 1
What is a Product Owner responsibility that he/she might delegate?
A. Representing stakeholders to the Scrum team
B. Attending the Sprint Review
C. Writing User Stories
D. Ordering the Product Backlog
Answer: D
Explanation:
The Development Team may need to order the Product Backlog as they would know the most about technical limitations, risks, or dependencies between Product Backlog Items. As User Stories is a localized practice, Scrum does not govern it or dictate the practice. How the team describes the items is up to them as long as it has enough information to be transparent and understood.
QUESTION NO: 2
A Development Team member has notified the Scrum Master of a potential data security risk.
What action should the Scrum Master take?
A. Ask the Development Team member to share the issue with the team as soon as possible.
B. Notify the test team.
C. Add a Product Backlog item to address the security issue.
D. Wait until the Sprint Retrospective to add security to the definition of "Done".
Answer: A
Explanation:
It is best to coach the Development Team members to collaborate on issues regardless of severity.
They may consult the Scrum Master of Product Owner if needed.
QUESTION NO: 3
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
QUESTION NO: 4
An organization has just hired you as a new Scrum Master to help them transition their teams from their current traditional process to Scrum. The teams are currently structured to specialize in a single function. This is also known as component teams where a team would only address a single layer (i.e. design, frontend, backend, database, testing, etc.). You've introduced the concept of cross- functional teams where all the skills needed to produce business functionality, from end to end, are inside of a single team.
What should you keep in mind when transitioning from siloed teams to cross-functional teams?
(Choose two.)
A. It is easier to compare the performance between cross-functional teams in order to identify to which teams to assign tasks and which teams need additional coaching.
B. Without feature teams, you cannot do Scrum. Postpone Scrum adoption until the teams are reorganized in feature teams.
C. People from the different layers and components will need time to become accustomed to working and delivering unified functionality together as one Scrum Team thus productivity may suffer.
D. Newly formed teams will need time to stabilize before reaching their peak performance. During the initial stages of forming, performance will suffer and productivity may be low, although even then delivery of business value is still likely to increase.
Answer: C,D
Explanation:
Forming a team takes time, and members often go through recognizable stages as they change from being a collection of strangers to a united group with common goals. Bruce Tuckman's Forming,
Storming, Norming, and Performing model describes these stages. When you understand it, you can help your new team become effective more quickly.
QUESTION NO: 5
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.
Our site is working on providing most helpful the real test questions answer in IT certification exams many years especially for Huawei H13-921_V1.5. For the first time, you need to open Scrum SAFe-Practitioner exam questions in online environment, and then you can use it offline. Fortinet NSE7_SOC_AR-7.6 - If you are a person who desire to move ahead in the career with informed choice, then the Scrum training material is quite beneficial for you. Not only our CIPS L4M5 study materials contain the latest exam questions and answers, but also the pass rate is high as 98% to 100%. Our website is here to lead you toward the way of success in Microsoft AZ-204-KR certification exams and saves you from the unnecessary preparation materials.