PSM-II Valid Test Simulator & Scrum Exam PSM-II Quiz - Professional Scrum Master Level Ii PSM-II - Goldmile-Infobiz

Originating the PSM-II Valid Test Simulator exam questions of our company from tenets of offering the most reliable backup for customers, and outstanding results have captured exam candidates’ heart for their functions. Our PSM-II Valid Test Simulator practice materials can be subdivided into three versions. All those versions of usage has been well-accepted by them. It is well known that Goldmile-Infobiz provide excellent Scrum PSM-II Valid Test Simulator exam certification materials. Many candidates do not have the confidence to win Scrum PSM-II Valid Test Simulator certification exam, so you have to have Goldmile-Infobiz Scrum PSM-II Valid Test Simulator exam training materials. Then, you will have enough confidence to pass your exam.

Professional Scrum Master PSM-II Our system is high effective and competent.

Professional Scrum Master PSM-II Valid Test Simulator - Professional Scrum Master level II (PSM II) Goldmile-Infobiz will provide you with the best training materials, and make you pass the exam and get the certification. If you have tried on our PSM-II Valid Test Collection Sheet exam questions, you may find that our PSM-II Valid Test Collection Sheet study materials occupy little running memory. So it will never appear flash back.

Within the last few decades, IT got a lot of publicity and it has been a necessary and desirable part of modern life. Scrum certification has been well recognized by international community. So, most IT people want to improve their knowledge and their skills by Scrum certification exam.

Scrum PSM-II Valid Test Simulator - PDF version is easy for read and print out.

You may strand on some issues at sometimes, all confusions will be answered by the bountiful contents of our PSM-II Valid Test Simulator exam materials. Wrong choices may engender wrong feed-backs, we are sure you will come a long way by our PSM-II Valid Test Simulator practice questions. In fact, a lot of our loyal customers have became our friends and only relay on our PSM-II Valid Test Simulator study braindumps. As they always said that our PSM-II Valid Test Simulator learning quiz is guaranteed to help them pass the exam.

Once you have well prepared with our PSM-II Valid Test Simulator dumps collection, you will go through the formal test without any difficulty. To help people pass exam easily, we bring you the latest PSM-II Valid Test Simulator exam prep for the actual test which enable you get high passing score easily in test.

PSM-II PDF DEMO:

QUESTION NO: 1
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C

QUESTION NO: 2
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.

QUESTION NO: 3
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C

QUESTION NO: 4
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.

QUESTION NO: 5
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.

Microsoft AB-100 - Though the content is the same, but the displays are different due to the different study habbits of our customers. So the HP HPE7-A03 questions & answers are valid and reliable to use. CompTIA N10-009 - Because we are all individual creature has unique requirement. You can get prepared with our EMC D-PSC-DS-01 exam materials only for 20 to 30 hours before you go to attend your exam. Salesforce Plat-101 study braindumps also offer a PDF mode that allows you to print the data onto paper so that you can take notes as you like and help you to memorize your knowledge.