Every year there are thousands of candidates choosing our products and obtain certifications so that our PSM-II Latest Exam Camp File valid exam simulations file is famous for its high passing-rate in this field. If you want to pass exam one-shot, you shouldn't miss our files. Quitters never win and winners never quit. After careful preparation, I believe you will be able to pass the exam. This is a wise choice, after using our PSM-II Latest Exam Camp File training materials, you will realize your dream of a promotion because you deserve these reports and your efforts will be your best proof. Our braindumps for PSM-II Latest Exam Camp File real exam are written to highest standard of technical profession, tested by our senior IT experts and certified trainers.
Professional Scrum Master PSM-II So you can take a best preparation for the exam.
We offer guaranteed success with PSM-II - Professional Scrum Master level II (PSM II) Latest Exam Camp File dumps questions on the first attempt, and you will be able to pass the PSM-II - Professional Scrum Master level II (PSM II) Latest Exam Camp File exam in short time. Goldmile-Infobiz's training tool has strong pertinence, which can help you save a lot of valuable time and energy to pass IT certification exam. Our exercises and answers and are very close true examination questions.
We see to it that our assessment is always at par with what is likely to be asked in the actual Scrum PSM-II Latest Exam Camp File examination. And If you’re skeptical about the quality of our Scrum PSM-II Latest Exam Camp File exam dumps, you are more than welcome to try our demo for free and see what rest of the PSM-II Latest Exam Camp File exam applicants experience by availing our products. Our methods are tested and proven by more than 90,000 successful Scrum certification examinees whose trusted Goldmile-Infobiz.
Scrum PSM-II Latest Exam Camp File - It will help us to pass the exam successfully.
In every area, timing counts importantly. With the advantage of high efficiency, our PSM-II Latest Exam Camp File practice materials help you avoid wasting time on selecting the important and precise content from the broad information. In such a way, you can confirm that you get the convenience and fast. By studying with our PSM-II Latest Exam Camp File real exam for 20 to 30 hours, we can claim that you can get ready to attend the PSM-II Latest Exam Camp Fileexam.
To get the Scrum PSM-II Latest Exam Camp File exam certification is the goal of many IT people & Network professionals. The pass rate of Goldmile-Infobiz is incredibly high.
PSM-II PDF DEMO:
QUESTION NO: 1
Which of the following are time-boxed events in Scrum?
A. Daily Scrum
B. Sprint Review
C. All of the above
D. Sprint Planning
E. Sprint Retrospective
Answer: C
QUESTION NO: 2
A Development Team has a total of six members, 4 members who work full time in the office and 2 members who work part time at home. The Development Team is complaining that it is too difficult to synchronize every day and has suggested having the Daily Scrum every other day instead.
What would be three key concerns if the Daily Scrum is held less frequently? (Choose three.)
A. The Scrum Master loses the ability to update the burndown chart adequately.
B. The Product Owner cannot accurately inspect utilization of the individual team members.
C. Impediments are raised and resolved more slowly.
D. Less information about the progress will be shared causing the Sprint plan to become inaccurate and reducing transparency over progress toward the Sprint Goal.
E. Opportunities to inspect and adapt the Sprint Backlog are reduced.
Answer: C,D,E
Explanation:
The Daily Scrum is an internal meeting for the Development Team to inspect progress toward the
Sprint Goal and to inspect how progress is trending toward completing the work in the Sprint
Backlog. The Daily Scrum optimizes the probability that the Development Team will meet the Sprint
Goal. Every day, the Development Team should understand how it intends to work together as a self- organizing team to accomplish the Sprint Goal and create the anticipated Increment by the end of the
Sprint.
Reducing the frequency of the event will increase the length of the feedback loop and adds risk if the team deviates too far off course.
QUESTION NO: 3
Which role would know the most about the progress toward a business objective or a release, and be able to explain clearly the alternatives?
A. The Release Manager
B. The Scrum Master
C. The Product Owner
D. The Development Team
Answer: C
QUESTION NO: 4
During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint. The Development Team does, however, mention that they were able to achieve a high velocity.
What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)
A. Facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable, even if the measured velocity drops in the next Sprint.
B. Agree and acknowledge the Development Team's hard work, so they will be motivated to do even more in the next Sprint.
C. Stress the value of working software over measured velocity.
D. Acknowledge the hard work but remind the Development Team that they need to improve in order to do even more in the next Sprint.
Answer: A,C
Explanation:
Scrum employs an iterative, incremental approach to optimize predictability and control risk. The primary objective of a Sprint (iteration) is to produce a potentially shippable product Increment.
Having an Increment will allow the Scrum Team to know the right thing to do in the upcoming Sprint.
Having a velocity is important but working software is the primary measure of progress.
QUESTION NO: 5
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint.
What should you do?
A. Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
B. The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
C. Wait until the technical writer returns before continuing with related items.
D. Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Answer: B
Explanation:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole.
Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
All customer information to purchase our HP HPE3-CL01 guide torrent is confidential to outsides. Microsoft MS-700 - Then, you need to upgrade and develop yourself. So you can see how you have done and know which kinds of questions of the Microsoft SC-300 exam are to be learned more. Huawei H25-521_V1.0 - Whatever exam you choose to take, Goldmile-Infobiz training dumps will be very helpful to you. Before the clients buy our Fortinet FCSS_NST_SE-7.4 guide prep they can have a free download and tryout.