Although we cannot contact with each other face to face, but there are no disparate treatments and we treat every customer with consideration like we are around you at every stage during your review process on our 1z0-062 Mock Exam exam questions. We will offer help insofar as I can. While our 1z0-062 Mock Exam training guide is beneficiary even you lose your chance of winning this time. Besides, the software version can simulate the real test environment, which is favorable for people to better adapt to the examination atmosphere. With the online version, you can study the 1z0-062 Mock Exam study materials wherever you like, and you still have access to the materials even if there is no internet available on the premise that you have studied the 1z0-062 Mock Exam study materials online once before. Just try our 1z0-062 Mock Exam learning braindumps, and you will be satisfied.
Oracle Database 1z0-062 Goldmile-Infobiz is worthful to choose.
Thousands of people tried the 1z0-062 - Oracle Database 12c: Installation and Administration Mock Exam exams, but despite having good professional experience and being well-prepared, the regrettable exam failed. About the Latest 1z0-062 Exam Cram Sheet exam certification, reliability can not be ignored. Latest 1z0-062 Exam Cram Sheet exam training materials of Goldmile-Infobiz are specially designed.
We can make sure that it will be very easy for you to pass your exam and get the related certification in the shortest time that beyond your imagination. As is known to us, there are best sale and after-sale service of the 1z0-062 Mock Exam study materials all over the world in our company. Our company has employed a lot of excellent experts and professors in the field in the past years, in order to design the best and most suitable 1z0-062 Mock Exam study materials for all customers.
Oracle 1z0-062 Mock Exam - If you miss it you will regret for a lifetime.
Do you want to try our free demo of the 1z0-062 Mock Exam study questions? Your answer must be yes. So just open our websites in your computer. You will have easy access to all kinds of free trials of the 1z0-062 Mock Exam practice materials. You can apply for many types of 1z0-062 Mock Exam exam simulation at the same time. Once our system receives your application, it will soon send you what you need. Please ensure you have submitted the right email address. And you will have the demos to check them out.
It not only can help you to pass the exam , you can also improve your knowledge and skills. Help you in your career in your advantage successfully.
1z0-062 PDF DEMO:
QUESTION NO: 1
Your database is open and the listener LISTENER is up. You issue the command:
LSNRCTL> RELOAD
What is the effect of RELOAD on sessions that were originally established by LISTENER?
A. Only sessions based on static listener registrations are disconnected.
B. The sessions are not affected and continue to function normally.
C. All the sessions are terminated and active transactions are rolled back.
D. Existing connections are not disconnected; however, they cannot perform any operations until the listener completes the re-registration of the database instance and service handlers.
Answer: B
QUESTION NO: 2
Which statement is true about Oracle Net Listener?
A. A single listener can service only one database instance and multiple remote client connections.
B. It acts as the listening endpoint for the Oracle database instance for all local and non-local user connections.
C. Service registration with the listener is performed by the process monitor (PMON) process of each database instance.
D. The listener.ora configuration file must be located in the ORACLE_HOME/network/admin directly.
E. The listener.ora configuration file must be configured with one or more listening protocol addresses to allow remote users to connect to a database instance.
Answer: C
Explanation
https://docs.oracle.com/database/121/CNCPT/process.htm
QUESTION NO: 3
Which two statements are true about the (PMON) background process in Oracle Database
12c? (Choose two.)
A. It frees unused temporary segments.
B. It kills sessions that exceed idle time.
C. It frees resources held by abnormally terminated processes.
D. It registers database services with all local and remote listeners known to the database instance.
E. It records checkpoint information in the control file.
Answer: C,D
Explanation
References: https://docs.oracle.com/database/122/CNCPT/process-architecture.htm#CNCPT9840
QUESTION NO: 4
Which two statements are true concerning the Resource Manager plans for individual pluggable databases (PDB plans) in a multitenant container database (CDB)? (Choose two.)
A. If a PDB plan is enabled for a pluggable database, then resources are allocated to consumer groups based on the shares provided to the PDB in the CDB plan and the shares provided to the consumer groups in the PDB plan.
B. If no PDB plan is enabled for a pluggable database, then all sessions for that PDB are treated to an equal degree of the resource share of that PDB.
C. If a PDB plan is enabled for a pluggable database, then resources are allocated to consumer groups across all PDBs in the CDB.
D. In a PDB plan, subplans may be used with up to eight consumer groups.
E. If no PDB plan is enabled for a pluggable database, then the PDB share in the CDB plan is dynamically calculated.
Answer: A,B
Explanation
A: Setting a PDB resource plan is optional. If not specified, all sessions within the PDB are treated equally.
* In a non-CDB database, workloads within a database are managed with resource plans.
In a PDB, workloads are also managed with resource plans, also called PDB resource plans.
The functionality is similar except for the following differences:
/ Non-CDB Database
Multi-level resource plans
Up to 32 consumer groups
Subplans
/ PDB Database
Single-level resource plans only
Up to 8 consumer groups
(not B) No subplans
QUESTION NO: 5
Which four statements are true about the components of the Oracle Scheduler? (Choose four.)
A. A job may get started automatically when a window opens.
B. A job is specified as part of a program specification.
C. A program can be used in the definition of multiple jobs.
D. A program and schedule can be specified as part of a job definition.
E. A scheduler job can point to a chain instead of pointing to a single program object.
F. A program and job can be specified as part of a schedule definition.
G. A schedule can be specified to a single job only.
Answer: A,C,D,E
Explanation
References: https://docs.oracle.com/cd/B19306_01/server.102/b14231/schedover.htm
CSI CSC2 - And we will try our best to satisfy our customers with better quatily and services. If you feel that you purchase Goldmile-Infobiz Oracle PMI PMP-KR exam training materials, and use it to prepare for the exam is an adventure, then the whole of life is an adventure. But they forgot to answer the other questions, our Microsoft AZ-104-KR training guide can help you solve this problem and get used to the pace. SAP C_ARSUM_2508 - Not having confidence to pass the exam, you give up taking the exam. They will accurately and quickly provide you with Oracle certification Pure Storage Portworx-Enterprise-Professional exam materials and timely update Oracle Pure Storage Portworx-Enterprise-Professional exam certification exam practice questions and answers and binding.