Constant improvement of the software also can let you enjoy more efficient review process of ACP-100 Books Pdf exam. The competition in IT industry is increasingly intense, so how to prove that you are indispensable talent? To pass the ACP-100 Books Pdf certification exam is persuasive. What we can do for you is to let you faster and more easily pass the ACP-100 Books Pdf exam. The customer is God. ACP-100 Books Pdf learning dumps provide all customers with high quality after-sales service. Try the ATLASSIAN ACP-100 Books Pdf free demo and assess the validity of our ACP-100 Books Pdf practice torrent.
Jira Administrator ACP-100 People’s tastes also vary a lot.
Our ACP-100 - Jira Administration for Data Center Books Pdf study guide is the most reliable and popular exam product in the marcket for we only sell the latest ACP-100 - Jira Administration for Data Center Books Pdf practice engine to our clients and you can have a free trial before your purchase. Professional research data is our online service and it contains simulation training examination and practice questions and answers about ATLASSIAN certification Latest ACP-100 Exam Dumps.Zip exam. Goldmile-Infobiz's after-sales service is not only to provide the latest exam practice questions and answers and dynamic news about ATLASSIAN Latest ACP-100 Exam Dumps.Zip certification, but also constantly updated exam practice questions and answers and binding.
All of them have passed the exam and got the certificate. They live a better life now. Our ACP-100 Books Pdf study guide can release your stress of preparation for the test.
ATLASSIAN ACP-100 Books Pdf - It is your right time to make your mark.
It is no longer an accident for you to pass ACP-100 Books Pdf exam after you have use our ACP-100 Books Pdf exam software. You will have thorough training and exercises from our huge question dumps, and master every question from the detailed answer analysis. The exam software with such guarantees will clear your worries about ACP-100 Books Pdf exam.
But our ACP-100 Books Pdf real exam is high efficient which can pass the ACP-100 Books Pdf exam during a week. To prevent you from promiscuous state, we arranged our ACP-100 Books Pdf learning materials with clear parts of knowledge.
ACP-100 PDF DEMO:
QUESTION NO: 1
You receive workflow configuration requirements for issues in the Closed status. They are as follows:
* Users must NOT be able to edit issues in this status.
* Jira administrators must be able to edit issues in this status.
* Only users in the release-managers group should see the transition to the Re-opened status Which combination of two workflow configuration items should you use to meet these requirements?
(Choose two.)
A. Conditions
B. Triggers
C. Validators
D. Properties
E. Post functions
Answer: A,C
QUESTION NO: 2
Tom has asked you why the numbers returned by his searches are not right. He shows you three JQL queries:
How can you fix this?
A. Change the query to project = "Cake Baking" and ( fixVersion is empty or fixVersion != 1.1.0 ).
B. Change the query to project = "Cake Baking" and fixVersion ~ 1.1.0.
C. Change the query to project = "Cake Baking" and fixVersion not in (1.1.0).
D. Identify the missing issues and change the permissions so that everyone can see them.
E. Rename the versions so they do not contain periods.
Answer: D
QUESTION NO: 3
You set up a new project for a team. Soon afterward, users report that a field is missing from one of their screens. You check the screen configuration in the administration panel and you see that the field should be present.
Why can't the users see the field?
A. The field context does not include the project and/or issue type.
B. The issue operation wasn't mapped to a screen.
C. The changes to the screen were not published.
D. The users don't have permission to view that field.
Answer: D
QUESTION NO: 4
Your organization has a Jira project for managing work on a software development project.
As the team has grown, two groups have formed within it, working on different tasks. To help bring more focus to the work being conducted, the team has requested a second Jira project to split the team's work into two.
Which set of schemes can likely be shared between the two projects?
A. Workflow and Custom Field
B. Notification and Workflow
C. Issue Type and Sub-task
D. Custom Field and Issue Security
E. Resolution and Notification
Answer: A
QUESTION NO: 5
An issue is showing the Time Tracking section as follows:
There is clearly an hour's difference between the Original and Remaining estimates.
Identify two possible reasons Logged Time is showing as Not Specified. (Choose two.)
A. The hour's work was logged via a REST call by the user.
B. Time tracking was not enabled when the work was logged.
C. The original estimate was increased.
D. The remaining estimate was adjusted without logging any effort.
E. You do not have view permission to see the logged work.
F. The work log would have exceeded the project's time allowance, so it cannot be counted.
Answer: B,D
We are not satisfied with that we have helped more candidates pass Adobe AD0-E725 exam, because we know that the IT industry competition is intense, we must constantly improve our dumps so that we cannot be eliminated. They always treat customers with courtesy and respect to satisfy your need on our Juniper JN0-650 exam dumps. Microsoft SC-100 - You just need to spend 20-30 hours for study and preparation, then confident to attend the actual test. SAP C-BCBTM-2502 - Our software is equipped with many new functions, such as timed and simulated test functions. Pegasystems PEGACPCSD25V1 - The contents of ATLASSIAN study dumps are edited by our experts who have rich experience, and easy for all of you to understand.