Our ACP-600 Test Duration exam braindumps are available for downloading without any other disturbing requirements as long as you have paid successfully, which is increasingly important to an examinee as he or she has limited time for personal study. Therefore, our Project Administration in Jira Server guide torrent is attributive to high-efficient learning. The immediate downloading feature of our ACP-600 Test Duration certification guide is an eminent advantage of our products. First, our ACP-600 Test Duration practice briandumps have varied versions as the PDF, software and APP online which can satify different needs of our customers. Secondly, the price is quite favourable. Although the ACP-600 Test Duration exam is an exam to test your mastery of the knowledge of ACP-600 Test Duration, but there are so many factor to influence the result.
Come and buy our ACP-600 Test Duration exam guide!
Unlike those untenable practice materials in the market, our ACP-600 - Project Administration in Jira Server Test Duration practice materials are highly utilitarian for their accuracy of the real exam because all content are compiled by proficient experts who engaged in this area more than ten years. Up to now, many people have successfully passed the Latest ACP-600 Exam Study Guide exam with our assistance. So you need to be brave enough to have a try.
By unremitting effort and studious research of the ACP-600 Test Duration actual exam, our professionals devised our high quality and high ACP-600 Test Duration effective practice materials which win consensus acceptance around the world. They are meritorious experts with a professional background in this line and remain unpretentious attitude towards our ACP-600 Test Duration preparation materials all the time. They are unsuspecting experts who you can count on.
ATLASSIAN ACP-600 Test Duration - The pass rate is the test of a material.
Add Goldmile-Infobiz's products to cart now! You will have 100% confidence to participate in the exam and disposably pass ATLASSIAN certification ACP-600 Test Duration exam. At last, you will not regret your choice.
Hope you can give our ACP-600 Test Duration exam questions full trust, we will not disappoint you. And with our ACP-600 Test Duration study materials, you are bound to pass the exam.
ACP-600 PDF DEMO:
QUESTION NO: 1
You are helping a manager to translate business requirements into a Jira project configuration.
The manager wants users to indicate which systems are impacted by a bug.
You are unsure if systems should be configured as components or as a custom field.
Select two situations in which components must definitely be used rather than a custom field.
(Choose two.)
A. Systems must have a default value.
B. Systems must be required on the screen.
C. Assignee must be set based on the selected system.
D. Users must be able to select multiple systems.
E. Systems must be managed by project administrators.
F. Systems must be exportable to CSV.
Answer: B,C
QUESTION NO: 2
You are asked to change who receives notifications when issues are moved.
The settings in the default notification scheme used by your project are shown in the table below.
As a project administrator, why are you NOT able to update the notification scheme?
A. You are not a Jira administrator.
B. The default notification scheme cannot be edited.
C. The extended project administration option is not enabled.
D. The notification scheme is shared.
Answer: A
QUESTION NO: 3
An extract of a permission scheme is shown below.
Jennifer Evans needs to be able to:
* Manage project role membership
* Log time to issues
What is the minimum number of project roles she needs?
A. 1
B. 3
C. 4
D. 2
Answer: B
QUESTION NO: 4
Below you are shown an extract of a field configuration used by all issue types in your project.
The field 'A detailed description' is a custom field of type Text field (multi-line). Which two statements are true? (Choose two.)
A. The field is mandatory in each issue type used in the project.
B. The project is configured to use only a single screen.
C. Users will be able to format text in the field.
D. The maximum text length is limited to 100 characters.
E. The field can only be used in combination with the Description system field.
Answer: C,E
QUESTION NO: 5
Your development team has just released their first version of a GPS tracker yesterday. The next product release is not due for another 3 months.
Which two JQL queries, when executed today, will list all features shipped in the 1.0 version? (Choose two.)
A. project = GPS AND type = Feature AND fixVersion in releasedVersions()
B. project = GPS AND type = Feature AND fixVersion in (1.0)
C. project = GPS AND issuetype = Feature AND fixVersion(s) IS NOT EMPTY
D. project = GPS AND type = Feature AND fixVersion(s) = "1.0"
E. project = GPS AND issuetype = Feature AND fixVersion in 1.0
F. project = GPS AND issuetype Feature AND fixVersion = released()
Answer: C,D
Microsoft SC-401 - Through our short-term special training You can quickly grasp IT professional knowledge, and then have a good preparation for your exam. The goal of our Medical Tests PTCE exam questions is always to get you through the Medical Tests PTCE exam. ISACA CISA-CN - We will provide one year free update service for those customers who choose Goldmile-Infobiz's products. If you have any worry about the SAP C-ARSUM-2508 exam, do not worry, we are glad to help you. Fortinet FCSS_SASE_AD-25 - As most of our exam questions are updated monthly, you will get the best resources with market-fresh quality and reliability assurance.
Updated: May 28, 2022