Our company always put the quality of the PK0-004 Latest Test Dumps Questions practice materials on top priority. In the past ten years, we have made many efforts to perfect our PK0-004 Latest Test Dumps Questions study materials. Our PK0-004 Latest Test Dumps Questions study questions cannot tolerate any small mistake. After your payment, we will send the updated PK0-004 Latest Test Dumps Questions exam to you immediately and if you have any question about updating, please leave us a message. In accordance with the actual exam, we provide the latest PK0-004 Latest Test Dumps Questions exam dumps for your practices. So we give emphasis on your goals, and higher quality of our PK0-004 Latest Test Dumps Questions practice materials.
Project+ PK0-004 You will know the effect of this exam materials.
Project+ PK0-004 Latest Test Dumps Questions - CompTIA Project+ Certification Exam You can download learning materials to your mobile phone and study at anytime, anywhere. It is a professional IT exam training site. With it, your exam problems will be solved.
Therefore, we sincerely wish you can attempt to our PK0-004 Latest Test Dumps Questions test question. Practice and diligence make perfect. Every one looks forward to becoming an excellent person.
CompTIA PK0-004 Latest Test Dumps Questions - Now let our Goldmile-Infobiz help you!
There are three different versions of our PK0-004 Latest Test Dumps Questions preparation prep including PDF, App and PC version. Each version has the suitable place and device for customers to learn anytime, anywhere. In order to give you a basic understanding of our various versions on our PK0-004 Latest Test Dumps Questions exam questions, each version offers a free trial. So there are three free demos of our PK0-004 Latest Test Dumps Questions exam materials. And you can easily download the demos on our website.
Goldmile-Infobiz insists on providing you with the best and high quality exam dumps, aiming to ensure you 100% pass in the actual test. Being qualified with CompTIA certification will bring you benefits beyond your expectation.
PK0-004 PDF DEMO:
QUESTION NO: 1
Which of the following documents should be used to provide high-level reporting to key stakeholders?
A. Dashboard
B. Communication plan
C. Statement of work
D. Project charter
Answer: A
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.
325
QUESTION NO: 2
A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?
A. The reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.
B. The reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.
C. The reduced timeline will decrease risk, resulting in an increased contingency reserve.
D. The reduced budget will cause the project manager to reject the change order.
Answer: B
QUESTION NO: 3
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
A. Compromising
B. Smoothing
C. Withdrawing
D. Accepting
Answer: C
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.
200
QUESTION NO: 4
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?
A. Forcing
B. Negotiating
C. Compromising
D. Avoiding
Answer: B
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.
200
QUESTION NO: 5
Which of the following Agile ceremonies is used to determine the backlog items that will be worked on the next weeks?
A. SCRUM retrospective meeting
B. Sprint planning meeting
C. Daily standup meeting
D. Review meeting
Answer: B
Explanation
References: https://www.atlassian.com/agile/ceremonies
Cisco 350-401 - We are now in an era of technological development. Now, VMware 2V0-16.25 sure pass exam will help you step ahead in the real exam and assist you get your VMware 2V0-16.25 certification easily. If you want to get the related certification in an efficient method, please choose the The Open Group OGBA-101 study materials from our company. DSCI DCPLA - If you want to pass exam one-shot, you shouldn't miss our files. This is a wise choice, after using our Fortinet FCSS_NST_SE-7.4 training materials, you will realize your dream of a promotion because you deserve these reports and your efforts will be your best proof.