To be convenient for the learners, our PK0-004 Valid Exam Questions Vce certification questions provide the test practice software to help the learners check their learning results at any time. Our PK0-004 Valid Exam Questions Vce study practice guide takes full account of the needs of the real exam and conveniences for the clients. Our PK0-004 Valid Exam Questions Vce certification questions are close to the real exam and the questions and answers of the test bank cover the entire syllabus of the real exam and all the important information about the exam. Our online staff is professionally trained and they have great knowledge on the PK0-004 Valid Exam Questions Vce study guide. So they can clearly understand your requirements and ideas and then help you make the right choices. CompTIA exam guide have to admit that the exam of gaining the CompTIA certification is not easy for a lot of people, especial these people who have no enough time.
Project+ PK0-004 It is quite convenient.
PK0-004 - CompTIA Project+ Certification Exam Valid Exam Questions Vce practice exam will provide you with wholehearted service throughout your entire learning process. If you are better, you will have a more relaxed life. Valid Study PK0-004 Questions Pdf guide materials allow you to increase the efficiency of your work.
Maybe you want to keep our PK0-004 Valid Exam Questions Vce exam guide available on your phone. Don't worry, as long as you have a browser on your device, our App version of our PK0-004 Valid Exam Questions Vce study materials will perfectly meet your need. That is to say that we can apply our App version on all kinds of eletronic devices, such as IPAD, computer and so on.
CompTIA PK0-004 Valid Exam Questions Vce study materials are here waiting for you!
The PK0-004 Valid Exam Questions Vce learning dumps from our company are very convenient for all people, including the convenient buying process, the download way and the study process and so on. Upon completion of your payment, you will receive the email from us in several minutes, and then you will have the right to use the CompTIA Project+ Certification Exam test guide from our company. In addition, there are three different versions for all people to choose. According to your actual situation, you can choose the suitable version from our PK0-004 Valid Exam Questions Vce study question. We believe that the suitable version will help you improve your learning efficiency. It will be very easy for you to pass the exam and get the certification. More importantly, your will spend less time on preparing for PK0-004 Valid Exam Questions Vce exam than other people.
We will adopt and consider it into the renovation of the PK0-004 Valid Exam Questions Vce exam guide. Anyway, after your payment, you can enjoy the one-year free update service with our guarantee.
PK0-004 PDF DEMO:
QUESTION NO: 1
A project sponsor and Chief Information Officer (CIO) disagree about how to release the final deliverables to the market. The sponsor wants to do a massive product release, while the CIO wants to be extremely cautious and add more time for testing and defect resolution. The project manager works with both parties and determines the best solution is to roll the product out in a pilot release to see how it tests, and then use customer feedback to determine next steps.
Which of the following conflict resolution techniques is the project manager using?
A. Forcing
B. Negotiating
C. Compromising
D. Avoiding
Answer: B
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.
200
QUESTION NO: 2
A project manager has received a change order that will reduce a project's timeline and budget. However, the change order also indicates the goals and deliverables of the project must remain unchanged. Which of the following is the MOST logical impact to the project?
A. The reduced timeline will impact the quality of the deliverables because the amount of time to test will be reduced.
B. The reduced budget will result in reduced resources, which will lead to a strong matrix organizational structure being used.
C. The reduced timeline will decrease risk, resulting in an increased contingency reserve.
D. The reduced budget will cause the project manager to reject the change order.
Answer: B
QUESTION NO: 3
A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?
A. Scope
B. Time
C. Quality
D. Cost
Answer: D
Explanation
References
https://programsuccess.wordpress.com/2011/05/02/scope-time-and-cost-managing-the-triple- constraint/
QUESTION NO: 4
Which of the following documents should be used to provide high-level reporting to key stakeholders?
A. Dashboard
B. Communication plan
C. Statement of work
D. Project charter
Answer: A
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p.
325
QUESTION NO: 5
A vendor was removed from a company due to non-performance but continues to submit invoices for work that was not completed. Which of the following should the project manager do to stop the vendor from sending invoices?
A. Draft a C&D letter and send it to vendor.
B. Review the MOU with the vendor.
C. Ask the legal departments to draft a non-complete agreement for the vendor to sign.
D. Meet with the finance department to prevent the vendor from sending invoices.
Answer: A
Microsoft AZ-700-KR - After careful preparation, I believe you will be able to pass the exam. Besides, the price of our Microsoft AZ-104-KR learning guide is very favourable even the students can afford it. Choosing our CompTIA 220-1102 learning guide is not only an enrichment of learning content, but also an opportunity to improve our own discovery space. Juniper JN0-460 - And we are grimly determined and confident in helping you. With our IBM C1000-205 study materials, you will pass the exam in the shortest possible time.