1Z0-1057 Simulations - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Latest Vce Test Simulator - Goldmile-Infobiz

Our company has spent more than 10 years on compiling 1Z0-1057 Simulations study materials for the exam in this field, and now we are delighted to be here to share our 1Z0-1057 Simulations learnign guide with all of the candidates for the exam in this field. There are so many striking points of our 1Z0-1057 Simulations preparation exam. If you want to have a better understanding of our 1Z0-1057 Simulations exam braindumps, just come and have a try! Our professional team checks the update of every exam materials every day, so please rest assured that the 1Z0-1057 Simulations exam software you are using must contain the latest and most information. Close to 100% passing rate is the best gift that our customers give us. Many people would like to fall back on the most authoritative company no matter when they have any question about preparing for 1Z0-1057 Simulations exam.

Oracle Project Portfolio Management Cloud 1Z0-1057 After all, you are the main beneficiary.

Oracle Project Portfolio Management Cloud 1Z0-1057 Simulations - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials With all these products, your success is assured with 100% money back guarantee. What’s more, all computers you have installed our study materials can run normally. Our Test 1Z0-1057 Simulator Free exam guide are cost-effective.

. The whole world of 1Z0-1057 Simulations preparation materials has changed so fast in the recent years because of the development of internet technology. We have benefited a lot from those changes.

Oracle 1Z0-1057 Simulations - You never know what you can get till you try.

There is a lot of data to prove that our 1Z0-1057 Simulations practice guide has achieved great success. First of all, in terms of sales volume, our 1Z0-1057 Simulations study materials are far ahead in the industry, and here we would like to thank the users for their support. Second, in terms of quality, we guarantee the authority of 1Z0-1057 Simulations study materials in many ways. You can just have a look at the pass rate of the 1Z0-1057 Simulations learning guide, it is high as 98% to 100% which is unique in the market.

We will tailor services to different individuals and help them take part in their aimed exams after only 20-30 hours practice and training. Moreover, we have experts to update 1Z0-1057 Simulations quiz torrent in terms of theories and contents according to the changeable world on a daily basis, which can ensure that you are not falling behind of others by some slight knowledge gaps.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset

QUESTION NO: 2
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 3
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 4
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

QUESTION NO: 5
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (
A. Project Accounting Business Function
B. Business Unit
C. Project Type
D. Organization Tree
E. Project Organization Classification
Answer: D,E
Explanation
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/FAPFM/FAPFM1225328.htm

We believe our IAPP CIPP-E actual question will help you pass the qualification examination and get your qualification certificate faster and more efficiently. So many our customers have benefited form our Microsoft DP-100 preparation quiz, so will you! Now if you go to the exam again, will you feel anxious? Huawei H13-324_V2.0 study guide can help you solve this problem. Our Salesforce Experience-Cloud-Consultant learning quiz is a salutary guidance helping you achieve success. To deliver on the commitments of our Fortinet FCP_FMG_AD-7.6 test prep that we have made for the majority of candidates, we prioritize the research and development of our Fortinet FCP_FMG_AD-7.6 test braindumps, establishing action plans with clear goals of helping them get the Oracle certification.