Our experts are working hard on our 1Z0-1057 Certification Cost exam questions to perfect every detail in our research center. Once they find it possible to optimize the 1Z0-1057 Certification Cost study guide, they will test it for many times to ensure the stability and compatibility. Under a series of strict test, the updated version of our 1Z0-1057 Certification Cost learning quiz will be soon delivered to every customer’s email box since we offer one year free updates so you can get the new updates for free after your purchase. And our 1Z0-1057 Certification Cost study materials always contain the latest exam Q&A. Even though we have already passed many large and small examinations, we are still unconsciously nervous when we face examination papers. Our 1Z0-1057 Certification Cost exam questions own a lot of advantages that you can't imagine.
Oracle Project Portfolio Management Cloud 1Z0-1057 PDF Version is easy to read and print.
1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Certification Cost test questions have very high quality services in addition to their high quality and efficiency. But if you are unfortunately to fail in the exam we will refund you in full immediately. Some people worry that if they buy our New 1Z0-1057 Exam Study Guide exam questions they may fail in the exam and the procedure of the refund is complicated.
We need to have more strength to get what we want, and 1Z0-1057 Certification Cost exam dumps may give you these things. After you use our study materials, you can get 1Z0-1057 Certification Cost certification, which will better show your ability, among many competitors, you will be very prominent. Using 1Z0-1057 Certification Cost exam prep is an important step for you to improve your soft power.
Oracle 1Z0-1057 Certification Cost - It is useless if you do not prepare well.
Our company has a professional team of experts to write 1Z0-1057 Certification Cost preparation materials and will constantly update it to ensure that it is synchronized with the exam content. In addition to the high quality, reasonable price and so on, we have many other reasons to make you choose our 1Z0-1057 Certification Cost actual exam. There are three versions of our 1Z0-1057 Certification Cost exam questions: PDF, Software and APP online which can provide you the varied study experiences.
Every day thousands of people browser our websites to select our 1Z0-1057 Certification Cost exam materials. As you can see, many people are inclined to enrich their knowledge reserve.
1Z0-1057 PDF DEMO:
QUESTION NO: 1
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works
QUESTION NO: 2
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm
QUESTION NO: 3
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In
QUESTION NO: 4
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset
QUESTION NO: 5
Which three tools are available for accessing REST APIs?
A. Web Browser
B. Oracle Transactional Business Intelligence
C. Programming Language
D. cURL
Answer: A,C,D
Explanation
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/18b/fapap/Use_cURL.html REST API = REpresentational State nterface (API)
The latest WGU Web-Development-Applications exam torrent covers all the qualification exam simulation questions in recent years, including the corresponding matching materials at the same time. Now Goldmile-Infobiz provide you a effective method to pass Oracle certification Microsoft AZ-120 exam. Our Huawei H19-401_V2.0 test practice guide’ self-learning and self-evaluation functions, the statistics report function, the timing function and the function of stimulating the test could assist you to find your weak links, check your level, adjust the speed and have a warming up for the real exam. PMI PMP-KR - Goldmile-Infobiz can also promise if you fail to pass the exam, Goldmile-Infobiz will 100% refund. EMC D-PWF-DS-01 - The more efforts you make, the luckier you are.
Updated: May 28, 2022