Now we would like to share the advantages of our 1Z0-1057 Sample Questions study dump to you, we hope you can spend several minutes on reading our introduction; you will benefit a lot from it. Our Oracle Project Portfolio Management Cloud 2019 Implementation Essentials exam questions are designed by a reliable and reputable company and our company has rich experience in doing research about the study materials. We can make sure that all employees in our company have wide experience and advanced technologies in designing the 1Z0-1057 Sample Questions study dump. Besides, rather than waiting for the gain of our 1Z0-1057 Sample Questions practice guide, you can download them immediately after paying for it, so just begin your journey toward success now. With our 1Z0-1057 Sample Questions learning questions, you will find that passing the exam is as easy as pie for our 1Z0-1057 Sample Questions study materials own 100% pass guarantee. After using the trial version, we believe that you will be willing to choose 1Z0-1057 Sample Questions exam questions.
Oracle Project Portfolio Management Cloud 1Z0-1057 In every area, timing counts importantly.
To get the Oracle 1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Sample Questions exam certification is the goal of many IT people & Network professionals. Our experts check whether there is an update on the Oracle Project Portfolio Management Cloud 2019 Implementation Essentials exam questions every day, if an update system is sent to the customer automatically. If you have any question about our 1Z0-1057 Examcollection Dumps test guide, you can email or contact us online.
And don't worry about how to pass the test, Goldmile-Infobiz certification training will be with you. What is your dream? Don't you want to make a career? The answer must be ok. Then, you need to upgrade and develop yourself.
Oracle 1Z0-1057 Sample Questions - Now, everything is different.
If you want to pass Oracle 1Z0-1057 Sample Questions exam and get a high paying job in the industry; if you are searching for the perfect 1Z0-1057 Sample Questions exam prep material to get your dream job, then you must consider using our Oracle Project Portfolio Management Cloud 2019 Implementation Essentials exam products to improve your skillset. We have curated new 1Z0-1057 Sample Questions questions answers to help you prepare for the exam. It can be your golden ticket to pass the Oracle 1Z0-1057 Sample Questions test on the first attempt. We are providing latest 1Z0-1057 Sample Questions PDF question answers to help you prepare exam while working in the office to save your time.
You will benefit a lot after you finish learning our 1Z0-1057 Sample Questions study materials just as our other loyal customers. Live in the moment and bravely attempt to totally new things.
1Z0-1057 PDF DEMO:
QUESTION NO: 1
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset
QUESTION NO: 2
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm
QUESTION NO: 3
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (
A. Project Accounting Business Function
B. Business Unit
C. Project Type
D. Organization Tree
E. Project Organization Classification
Answer: D,E
Explanation
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/FAPFM/FAPFM1225328.htm
QUESTION NO: 4
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works
QUESTION NO: 5
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In
It will help you to pass SAP C-ARCON-2508 exam successfully after a series of exercises, correction of errors, and self-improvement. CWNP CWNA-109 - We would like to tell you how to buy the most suitable and helpful study materials. The crucial thing when it comes to appearing a competitive exam like Network Appliance NS0-014 knowing your problem-solving skills. Cisco 400-007 - Then it is time for others to envy your luxury life. Pegasystems PEGACPSA24V1 - With all these products, your success is assured with 100% money back guarantee.