1Z0-1057 Top Dumps - Oracle Valid Test Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Questions Vce - Goldmile-Infobiz

The APP online version of our 1Z0-1057 Top Dumps real exam boosts no limits for the equipment being used and it supports any electronic equipment and the off-line use. If only you open it in the environment with the network for the first time you can use our 1Z0-1057 Top Dumps training materials in the off-line condition later. It depends on the client to choose the version they favor to learn our 1Z0-1057 Top Dumps study materials. In Goldmile-Infobiz's website you can free download study guide, some exercises and answers about Oracle certification 1Z0-1057 Top Dumps exam as an attempt. So why still hesitate? Act now, join us, and buy our 1Z0-1057 Top Dumps study materials.

Oracle Project Portfolio Management Cloud 1Z0-1057 The procedure of refund is very simple.

Goldmile-Infobiz will help you to find what you need in the exam and our dumps must help you to obtain 1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Top Dumps certificate. No one lose interest during using our Updated 1Z0-1057 Demo actual exam and become regular customers eventually. With free demos to take reference, as well as bountiful knowledge to practice, even every page is carefully arranged by our experts, our Updated 1Z0-1057 Demo exam materials are successful with high efficiency and high quality to navigate you throughout the process.

If you successfully get Oracle 1Z0-1057 Top Dumps certificate, you can finish your work better. Although the test is so difficult, with the help of Goldmile-Infobiz exam dumps you don't need so hard to prepare for the exam. After you use Goldmile-Infobiz Oracle 1Z0-1057 Top Dumps study guide, you not only can pass the exam at the first attempt, also can master the skills the exam demands.

To help you pass the Oracle 1Z0-1057 Top Dumps exam is our goal.

Our 1Z0-1057 Top Dumps study tools not only provide all candidates with high pass rate study materials, but also provide them with good service. If you have some question or doubt about us or our products, you can contact us to solve it. The thoughtfulness of our 1Z0-1057 Top Dumps study guide services is insuperable. What we do surly contribute to the success of 1Z0-1057 Top Dumps practice materials.We all know that it is of great important to pass the 1Z0-1057 Top Dumps exam and get the certification for someone who wants to find a good job in internet area. I will recommend our study materials to you. It can be said that our 1Z0-1057 Top Dumps test prep greatly facilitates users, so that users cannot leave their homes to know the latest information.

Our products are just suitable for you. Our 1Z0-1057 Top Dumps exam training dumps will help you master the real test and prepare well for your exam.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (
A. Project Accounting Business Function
B. Business Unit
C. Project Type
D. Organization Tree
E. Project Organization Classification
Answer: D,E
Explanation
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/FAPFM/FAPFM1225328.htm

QUESTION NO: 2
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset

QUESTION NO: 3
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 4
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 5
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

The Open Group OGEA-103 - And we have been treated as the most popular vendor in this career and recognised as the first-class brand to the candidates all over the world. You will get your CIPS L4M6 certification with little time and energy by the help of out dumps. Fortinet FCSS_NST_SE-7.4 - We are willing to deal with your problems. As we all know, it is not an easy thing to gain the ASQ CPGP certification. In a word, our Workday Workday-Pro-Compensation training braindumps will move with the times.

Updated: May 28, 2022