1Z0-1057 Reliable Exam Duration - Oracle New Test 1Z0-1057 Camp Pdf - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials - Goldmile-Infobiz

it can help you to pass the IT exam. With the Goldmile-Infobiz's Oracle 1Z0-1057 Reliable Exam Duration exam training materials, you will have better development in the IT industry. You can enjoy the treatment of high-level white-collar, and you can carve out a new territory in the internation. On the other hand, we offer this after-sales service to all our customers to ensure that they have plenty of opportunities to successfully pass their 1Z0-1057 Reliable Exam Duration actual exam and finally get their desired certification of 1Z0-1057 Reliable Exam Duration practice materials. The great advantage of our 1Z0-1057 Reliable Exam Duration study prep is that we offer free updates for one year long. It will help us to pass the exam successfully.

Oracle Project Portfolio Management Cloud 1Z0-1057 In every area, timing counts importantly.

To get the Oracle 1Z0-1057 - Oracle Project Portfolio Management Cloud 2019 Implementation Essentials Reliable Exam Duration exam certification is the goal of many IT people & Network professionals. All customer information to purchase our 1Z0-1057 Relevant Questions guide torrent is confidential to outsides. You needn’t worry about your privacy information leaked by our company.

Then, you need to upgrade and develop yourself. You worked in the IT industry, through what methods can you realize your dream? Taking IT certification exam and getting the certificate are the way to upgrade yourself. At present, Oracle 1Z0-1057 Reliable Exam Duration exam is very popular.

Oracle 1Z0-1057 Reliable Exam Duration - Then you will be confident in the actual test.

The 1Z0-1057 Reliable Exam Duration quiz torrent we provide is compiled by experts with profound experiences according to the latest development in the theory and the practice so they are of great value. Please firstly try out our product before you decide to buy our product. It is worthy for you to buy our 1Z0-1057 Reliable Exam Duration exam preparation not only because it can help you pass the exam successfully but also because it saves your time and energy. Your satisfactions are our aim of the service and please take it easy to buy our 1Z0-1057 Reliable Exam Duration quiz torrent.

Well-pointed preparation for your test will help you save a lot of time. Oracle 1Z0-1057 Reliable Exam Duration exam cram PDF will be great helper for your coming exam definitely.

1Z0-1057 PDF DEMO:

QUESTION NO: 1
Your customer has separate organizations to maintain indirect, capital, and billing types of projects.
Identify the two setups that can be used to fulfill this requirement. (
A. Project Accounting Business Function
B. Business Unit
C. Project Type
D. Organization Tree
E. Project Organization Classification
Answer: D,E
Explanation
Reference https://docs.oracle.com/cloud/latest/projectcs_gs/FAPFM/FAPFM1225328.htm

QUESTION NO: 2
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement.
(Choose the best answer.)
A. Spread Evenly
B. Current Cost
C. Actual Unit
D. Estimated Cost
E. Standard Unit Cost
Answer: B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project- foundation-configuration Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type.
You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly
Equal allocation of cost to each asset

QUESTION NO: 3
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)
A. common costs on the project/task
B. expenditure items whose cost spreads across multiple assets that are capitalized
C. expenditure type exclusions on the Capitalized Interest rate name
D. expenditure items whose costs are applied to a single asset or multiple assets
E. expenditure type exclusions on the Capitalized Interest rate schedules
Answer: D
Explanation
Reference
https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_988B43C997365159E040D30A68813832
https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49622/F1125377AN61D92.htm

QUESTION NO: 4
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
A. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
B. Unaccounted transactions have not been swept to the next period.
C. The corresponding Oracle Payables Cloud accounting period has not been closed.
D. Pending burden summarization items have not been processed.
E. Unaccounted transactions are not imported.
Answer: A,B
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record- accounting-for-project-bil Topic - Accounting Period and Project Accounting Period Closing: How
Validation Works

QUESTION NO: 5
Which five steps are required for the File-Based Data Import Integration option?
A. Import data into various applications.
B. Populate the spreadsheet with data and generate a CSV file.
C. Download an Excel template.
D. Upload the file to the server.
E. Run Process to transfer data to interface tables.
F. Install an Excel add-in.
Answer: B,C,D,E,F
Explanation
Ref:
https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_In

Juniper JN0-336 - The new supplemental updates will be sent to your mailbox if there is and be free. The Fortinet NSE7_SSE_AD-25 real questions are written and approved by our It experts, and tested by our senior professionals with many years' experience. So before your purchase you can have an understanding of our product and then decide whether to buy our Microsoft AB-730 study questions or not. Oracle training pdf material is the valid tools which can help you prepare for the Oracle N16291GC10 actual test. ServiceNow CIS-HAM - By actually simulating the test environment, you will have the opportunity to learn and correct self-shortcoming in study course.