If you are better, you will have a more relaxed life. 1Z0-1075 Practice Exam Online guide materials allow you to increase the efficiency of your work. You can spend more time doing other things. Maybe you want to keep our 1Z0-1075 Practice Exam Online exam guide available on your phone. Don't worry, as long as you have a browser on your device, our App version of our 1Z0-1075 Practice Exam Online study materials will perfectly meet your need. To meet the needs of users, and to keep up with the trend of the examination outline, our products will provide customers with larest version of our products.
1Z0-1075 Practice Exam Online study materials are here waiting for you!
Manufacturing Cloud 1Z0-1075 Practice Exam Online - Oracle Manufacturing and Maintenance Cloud 2019 Implementation Essentials We believe that the suitable version will help you improve your learning efficiency. We will adopt and consider it into the renovation of the 1Z0-1075 Reliable Exam Dumps Questions exam guide. Anyway, after your payment, you can enjoy the one-year free update service with our guarantee.
After careful preparation, I believe you will be able to pass the exam. Our {CertName} exam question is widely known throughout the education market. Almost all the candidates who are ready for the qualifying examination know our products.
Oracle 1Z0-1075 Practice Exam Online - Time and tides wait for no people.
Our 1Z0-1075 Practice Exam Online study quiz are your optimum choices which contain essential know-hows for your information. If you really want to get the certificate successfully, only 1Z0-1075 Practice Exam Online guide materials with intrinsic contents can offer help they are preeminent materials can satisfy your both needs of studying or passing with efficiency. For our 1Z0-1075 Practice Exam Online exam braindumps contain the most useful information on the subject and are always the latest according to the efforts of our professionals.
you may like our 1Z0-1075 Practice Exam Online exam materials since they contain so many different versions. You can use it anytime, anywhere.
1Z0-1075 PDF DEMO:
QUESTION NO: 1
You are reviewing the production status of your manufacturing plant shop floor as a production supervisor.
Your production manager wants a report on a work order status which is reserved against a particula r
customer. The final assembly of the work order is serialized.
Which option shows the steps to complete the task using the mobile application?
A. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode
to open the work order details page > Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, and click Send.
B. Select the infotile Customer to open the work order details page> Click Actions and select the E- mail
icon> Select required work orders>Select the e-mail client, enter the recipient's e-mail, and click
Send.
C. Search the work order by customer name to open the work order details page> Click Actions and select
the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, and
click Send.
D. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode
to open the work order details page> Select required work orders> Click Social icon (OSN) > Select recipient, and click Share.
Answer: A
QUESTION NO: 2
The Plant Manager informs you that they have bought several machines for their manufacturing plant ABC.
The plant has been set up with a separate cost element set ABC in Manufacturing Cloud. You are requested to
configure these machines in such a way that those are costed to the work order for which operations are
performed on these machines.
Identify the correct setup that you will advise to the Plant Manager.
A. Set up the machines as cost element type of "Resource" by selecting Cost Element set AB
B. Set up the machines as cost element type of "Overhead" by selecting Cost Element set ABC.
C. Set up the machines as cost element type of "Resource" by selecting Cost Element set Common.
D. Set up the machines as cost element type of "Overhead" by selecting Cost Element set Common.
Answer: C
QUESTION NO: 3
During a Manufacturing Cloud implementation, the customer request to develop Oracle
Transactional
Business Intelligence reports that are not available out-of- the box.
Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop the reports.
A. Oracle Business Intelligence Application
B. Oracle Business Intelligence Enterprise Edition
C. Oracle Business Intelligence Publisher
D. Oracle Business Intelligence Standard Edition
Answer: C
QUESTION NO: 4
A Production Operator needs to load Work Order Transactions from an external system into
Manufacturing
Cloud.
Identify the correct sequence of tasks to be performed.
A. Load Data to Fusion repository> Export File to UCM server > Process Import Operations
Transactions>
Load file from UCM to Interface table.
B. Load Data to Fusion repository> Export File to UCM server > Load file from UCM to Interface table
>Process Import Operations Transactions.
C. Load Data to Fusion repository> Load File from UCM to Interface table> Export File to UCM server>
Process Import Operations Transactions.
D. Export File to UCM server> Load Data to Fusion repository> Process Import Operations
Transactions>
Load file from UCM to Interface table.
Answer: D
QUESTION NO: 5
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items
with some overlap between them in terms of products manufactured. The distribution centers stock parts from
all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues.
This team
defines the items and sets the attributes for most parameters. The respective distribution centers and
manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.
A. Set up Plants as Inventory Organizations, Distribution Centers as Item Organizations, and
Corporate
Engineering organization as Item Organization.
B. Set up Plants as Inventory Organizations, Distribution Centers as Item Organizations, and
Corporate
Engineering organization as Inventory Organization.
C. Set up Plants as Inventory Organizations, Distribution Centers as Inventory Organizations, and
Corporate Engineering organizations as Item Organization.
D. Set up Plants and Distribution Centers as Inventory organizations and Corporate Engineering organization as Inventory Organization.
E. Set up Plants and Distribution Centers as Inventory organizations and Corporate Engineering organization as Item Organization
Answer: C,E
Our IIA IIA-CIA-Part2 study questions are so popular that everyday there are numerous of our loyal customers wrote to inform and thank us that they passed their exams for our exam braindumps. Not only because that our SAP C_SIGVT_2506 study materials can work as the guarantee to help them pass, but also because that our SAP C_SIGVT_2506 learning questions are high effective according to their accuracy. As you can see that on our website, we have free demos of the Nutanix NCP-MCI-6.10 study materials are freebies for your information. Therefore it is necessary to get a professional CIPS L5M10 certification to pave the way for a better future. With Adobe AD0-E124 exam torrent, you no longer need to spend money to hire a dedicated tutor to explain it to you, even if you are a rookie of the industry, you can understand everything in the materials without any obstacles.