But it is not easy to pass the exam. However, in fact, as long as you choose a good training materials to pass the exam is not impossible. We Goldmile-Infobiz ISQI CTAL-TM_Syll2012 Exam Question exam training materials in full possession of the ability to help you through the certification. If you are still hesitate to choose our Goldmile-Infobiz, you can try to free download part of ISQI CTAL-TM_Syll2012 Exam Question exam certification exam questions and answers provided in our Goldmile-Infobiz. So that you can know the high reliability of our Goldmile-Infobiz. One is PDF, and other is software, it is easy to download.
ISQI Certifications CTAL-TM_Syll2012 My dream is to become a top IT expert.
ISQI Certifications CTAL-TM_Syll2012 Exam Question - ISTQB Certified Tester Advanced Level - Test Manager [Syllabus 2012] Many people think that passing some difficult IT certification exams needs to be proficient in much of IT expertise and only these IT personnels who grasp the comprehensive IT knowledge would be able to enroll in the exam. With Goldmile-Infobiz ISQI CTAL-TM_Syll2012 Latest Mock Exam exam training materials, you can begin your first step forward. When you get the certification of ISQI CTAL-TM_Syll2012 Latest Mock Exam exam, the glorious period of your career will start.
Goldmile-Infobiz can provide you a pertinence training and high quality exercises, which is your best preparation for your first time to attend ISQI certification CTAL-TM_Syll2012 Exam Question exam. Goldmile-Infobiz's exercises are very similar with the real exam, which can ensure you a successful passing the ISQI certification CTAL-TM_Syll2012 Exam Question exam. If you fail the exam, we will give you a full refund.
ISQI CTAL-TM_Syll2012 Exam Question - Second, focus.
The happiness from success is huge, so we hope that you can get the happiness after you pass CTAL-TM_Syll2012 Exam Question exam certification with our developed software. Your success is the success of our Goldmile-Infobiz, and therefore, we will try our best to help you obtain CTAL-TM_Syll2012 Exam Question exam certification. We will not only spare no efforts to design CTAL-TM_Syll2012 Exam Question exam materials, but also try our best to be better in all after-sale service.
With it, you will pass the exam and achieve excellent results, towards your ideal place. Goldmile-Infobiz can provide professional and high quality products.
CTAL-TM_Syll2012 PDF DEMO:
QUESTION NO: 1
The following are the requirements identified as "critical":
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase
REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart
REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher
REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard
REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards (Visa, MasterCard and Great Wall Card)
REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the
"select" and "purchase" pages going back to the "browse" page (anonymous navigation)
Moreover the following quality risk item has been identified as "critical":
QR-P1. The web customer portal might not be able to provide the expected response time (less than
10 sec) for the purchase transactions under a load of up-to 1000 concurrent users
Test analysis for system testing has just begun and the following test conditions have been identifieD.
TC-SEL-01. Test the combinations of products and durations to define an item to purchase
TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart
TC-PUR-01. Test the purchase of an item
TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
K3 2 credits
A. 1
B. 2
C. 3
D. 4
Answer: C
QUESTION NO: 2
You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell special packages in their wine shops.
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the system testinG. EXCR1- Each "critical" quality risk item must be covered by at least one test condition EXCR2- Each "critical" requirement must be covered by at least one test condition
The following are the "critical" requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time
REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles,
6-bottles, 12-bottles, 15-bottles)
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and no more bottles than the package size. No error messages shall be displayed if the user selects a valid number of bottles (at least 1 bottle and no more than the package size)
REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid number of bottles is selected by the user (zero bottles or a number higher than the package size)
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa,
MasterCard, American Express)
REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card data are given by the user
QUSTION NO: 11 The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user
Test analysis for system testing has just begun and the following test conditions have been identifieD.
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user
Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete and correct, and covers the
REQSEL-4 requirement?
K3 2 credits
A. Select a 6-bottles package, then try to insert 5 bottles; verify that no error messages are displayed
B. Select a 6-bottles package, then try to insert 7 bottles; verify that no error messages are displayed
C. Select a 6-bottles package, then try to insert 7 bottles; verify that the "Invalid number of bottles" message is displayed
D. Select a 6-bottles package, then try to insert 7 bottles
Answer: C
QUESTION NO: 3
Which of the following is an example of the test closure activity indicated as "lessons learned"?
K2 1 credit
A. Archive all the test results of the acceptance testing phase
B. Deliver a list of the open defects of a software product released into production to the service desk team
C. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
D. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing
Answer: C
QUESTION NO: 4
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
K2 1 credit
A. A traceability matrix showing the relationships between the product risk items and the test cases
B. A list of all the open defects with the associated classification information extracted from the defect tracking system
C. A chart, showing the trend in the lag time from defect reporting to resolution, extracted from the defect tracking system
D. The execution status of all the test cases extracted from the test management tool
Answer: C
QUESTION NO: 5
You are the Test Manager for a project to develop a client-server application that allows wine vendors to order custom-assorted packages of wines of several winemakers to sell special packages in their wine shops.
You decide to apply a blended risk-based and reactive testing strategy. Below the exit criteria for the system testinG.
EXCR1- Each "critical" quality risk item must be covered by at least one test condition
EXCR2- Each "critical" requirement must be covered by at least one test condition
The following are the "critical" requirements of the application:
REQ-SEL-1. The application shall allow the user to order only one package at a time
REQ-SEL-2. The application shall allow the user to select between four different packages (2bottles,
6-bottles, 12-bottles, 15-bottles)
REQ-SEL-3. The application shall allow the user to order a package containing at least 1 bottle and no more bottles than the package size. No error messages shall be displayed if the user selects a valid number of bottles (at least 1 bottle and no more than the package size)
REQ-SEL-4. The application shall display an error message "Invalid number of bottles" if an invalid number of bottles is selected by the user (zero bottles or a number higher than the package size)
REQ-PAY-1. The application shall allow the user to pay with the three accepted credit cards (Visa,
MasterCard, American Express)
REQ-PAY-2. The application shall display an error message "Invalid credit card" if invalid credit card data are given by the user
The following is the unique "critical" quality risk item that has been identified:
CR-RSK-1. The GUI of the application might accept non-integer values for the input field designed to get the number of bottles from the user Test analysis for system testing has just begun and the following test conditions have been identified.
TC-SEL-2. Test the selection of the package sizes
TC-SEL-4. Test wrong numbers of bottles for an order
TC-CR-RSK-1. Test the accepted values from the input field designed to get the number of bottles from the user
What is the MINIMUM number of test conditions that must be added to fulfill both the EXCR1 and
EXCR2 exit criteria?
K3 2 credits
A. 4
B. 3
C. 2
D. 1
Answer: A
In order to let you be rest assured to purchase our products, we offer a variety of versions of the samples of Juniper JN0-650 study materials for your trial. Fortinet FCP_FSM_AN-7.2 - You can also request we provide you with the latest dumps at any time. If you prepare based on our Fortinet NSE6_SDW_AD-7.6 exam simulations files, you will feel easy to clear exam once certainly. Fortinet FCP_FGT_AD-7.6 - Goldmile-Infobiz has everything you need and can absolutely satisfy your demands. Purchasing valid Microsoft PL-600 exam dumps is not a cheap thing for some candidates in the internet since there is so much different advertisement.